[CC 1995 § 49.010]
It shall be unlawful for any person to dig up, break, excavate, tunnel, undermine or cause to be made any excavation in or under the surface of any street or alley or public or private property by a mechanical digger or earth mover, for any purpose, excepting herefrom, however, any manual performed labor by pick and shovel or similar manual powered equipment on private property, unless such person shall first have obtained an excavation permit from the City of Golden City as provided herein.
[CC 1995 § 49.020]
Application for permit shall be made at the office of the City Clerk and approved by the Public Works Director and/or the Mayor, subject to the regulations herein provided.
[CC 1995 § 49.030]
A person, firm or corporation operating a mechanical digger or earth mover shall furnish the City Clerk, or other designated individual, a certificate of effective public liability and property damage insurance equal to or more than five thousand dollars ($5,000.00) a person, one million dollars ($1,000,000.00) each accident and one hundred thousand dollars ($100,000.00) property damage. Said certificate of insurance shall also be accompanied by a certified performance bond in an amount as required by the project engineer.
[CC 1995 § 49.040]
Excavation work, either by machinery or manual labor, shall be performed and conducted so as not to interfere with access to fire stations or fire hydrants. Materials or obstructions shall not be placed within, fifteen (15) feet of fire plugs.
[CC 1995 § 49.050]
A. 
Permittees working on streets or alleys or private roads shall erect proper barriers for daytime use and suitable flares so as to safeguard the flow of traffic.
1. 
Permittees crossing sidewalks or normal foot passageways shall erect proper barriers so as to prevent individuals from falling into any excavation the permittee is responsible for.
[CC 1995 § 49.060]
A. 
Permittee shall not interfere with an existing utility without written consent of the owner of the utility.
1. 
Permittee shall not interfere with existing City water or sewerage lines and shall not dig, by machine, closer than three (3) feet to any existing sewer main. The last three (3) feet must be dug manually using extreme caution not to injure in any manner an existing sewer main.
[CC 1995 § 49.070]
Permittee shall at all times make every effort not to interfere or injure any adjoining property and shall take appropriate protective measures.
[CC 1995 § 49.080]
It shall be unlawful for the permittee to suffer or permit to remain unguarded at the place of excavation any machinery, equipment or other device having the characteristics of an attractive nuisance likely to attract children and hazardous to their safety or health.
[CC 1995 § 49.090]
Backfilling shall be done to comply with the requirements of the City Engineer.
[CC 1995 § 49.100]
After completion of backfill, inspection shall be made of excavations where City water or sewer lines are involved, and if the Inspector shall require additional work in order to comply with the requirements of Section 520.090 above, the permittee shall cause said requirements to be promptly made.
[CC 1995 § 49.110]
A. 
Resurfacing of all streets, alleys or traffic passageways excavated by permittee under provisions of this Chapter shall be made and performed by the City of Golden City under the supervision of the City Engineer.
1. 
Permittee shall bear the expense incurred by the City while resurfacing said excavation.