For areas not covered by a release rate map from an approved Act
167 Stormwater Management Plan, post-development discharge rates shall
not exceed the predevelopment discharge rates for the one-, two-,
five-, ten-, twenty-five-, fifty-, and 100-year, twenty-four-hour
storm events. This is the equivalent to a 100% release rate area when
compared to those rates shown in the maps contained in Appendix A.
This predevelopment to post-development control is not to be misconstrued
as the same as the "conditional direct discharge" areas on the release
rate maps. If it is shown that the peak rates of discharge indicated
by the post-development analysis are less than or equal to the peak
rates of discharge indicated by the predevelopment analysis for one-,
two-, five-, ten-, twenty-five-, fifty-, and 100-year, twenty-four-hour
storms, then the requirements of this section have been met. Otherwise,
the applicant shall provide additional controls as necessary to satisfy
the peak rate of discharge requirement. Peak flows should be computed
using the methods included in the chapter titled "Stormwater Calculations
and Methodology" of the PADEP Stormwater Management BMP Manual.