[Ord. No. 760 § 30-14.1]
The soil erosion and sediment control plan approved by the Somerset-Union
Soil Conservation District or any approved soil erosion plan shall
remain in full force and effect during the course of construction
of the entire project. Failure to comply with the soil erosion and
sediment control plans shall result in a work stoppage until the conditions
are corrected and the plan reimplemented.
[Ord. No. 760 § 30-14.4]
Prior to construction, including site work activity, a preconstruction
meeting shall be required to include the Borough representatives,
the applicant and its engineers and contractors. The preconstruction
meeting shall not be held until inspection fees and performance bonds
have been submitted and approved by the Borough Attorney. Four (4)
sets of plans containing all corrections, additions and deletions
required by the approving Board and all other prior approved permits
shall be provided at least five (5) days prior to the preconstruction
meeting. Copies of all permits from the Federal, State and County
agencies shall be provided at the meeting.