The green infrastructure and low impact development practices
provided in the BMP Manual shall be utilized for all regulated activities
wherever possible. Water volume controls shall be implemented using
the Design Storm Method in Subsection A or the Simplified Method in
Subsection B below. For regulated activity areas equal or less than
one acre that do not require hydrologic routing to design the stormwater
facilities, this chapter establishes no preference for either methodology;
therefore, the applicant may select either methodology on the basis
of economic considerations, the intrinsic limitations on applicability
of the analytical procedures associated with each methodology and
other factors.
A. The Design Storm Method (CG-1 in the BMP Manual) is applicable to
any size of regulated activity. This method requires detailed modeling
based on site conditions.
(1) Do not increase the post-development total runoff volume for all
storms equal to or less than the two-year, twenty-four-hour duration
precipitation.
(2) For modeling purposes:
(a)
Existing (predevelopment) nonforested pervious areas must be
considered meadow in good condition.
(b)
(Enter a percentage no less than 20%, up to 100%) of existing
impervious area, when present, shall be considered meadow in good
condition in the model for existing conditions.
B. The Simplified Method (CG-2 in the BMP Manual) provided below is
independent of site conditions and should be used if the Design Storm
Method is not followed. This method is not applicable to regulated
activities greater than one acre or for projects that require design
of stormwater storage facilities. For new impervious surfaces:
(1) Stormwater facilities shall capture at least the first two inches
of runoff from all new impervious surfaces.
(2) At least the first one inch of runoff from new impervious surfaces
shall be permanently removed from the runoff flow, i.e., it shall
not be released into the surface waters of this commonwealth. Removal
options include reuse, evaporation, transpiration, and infiltration.
(3) Whenever possible, infiltration facilities should be designed to
accommodate infiltration of the entire permanently removed runoff;
however, in all cases at least the first 0.5 inch of the permanently
removed runoff should be infiltrated.
(4) This method is exempt from the requirements of §
155-15, Rate controls.