A. 
The Town shall ensure that preventative maintenance is performed by the owner by inspecting all stormwater management systems. Inspection shall occur during the first year of operation and at least once every three years thereafter. In addition, a maintenance agreement between the owner and the Town shall be executed for privately owned ESD treatment practices and structural stormwater management measures as described in § 106-25 of this chapter.
B. 
Inspection reports shall be maintained by the Town for all stormwater management systems.
C. 
Inspection reports for stormwater management systems shall include the following:
(1) 
The date of inspection;
(2) 
Name of inspector;
(3) 
An assessment of the quality of the stormwater management system related to ESD treatment practice efficiency and the control of runoff to the MEP;
(4) 
The condition of:
(a) 
Vegetation or filter media;
(b) 
Fences or other safety devices;
(c) 
Spillways, valves, or other control structures;
(d) 
Embankments, slopes, and safety benches;
(e) 
Reservoir or treatment areas;
(f) 
Inlet and outlet channels or structures;
(g) 
Underground drainage;
(h) 
Sediment and debris accumulation in storage and forebay areas;
(i) 
Any nonstructural practices to the extent practicable; and
(j) 
Any other item that could affect the proper function of the stormwater management system.
(5) 
Description of needed maintenance.
D. 
Upon notifying an owner of the inspection results, the owner shall have 30 days, or other time frame mutually agreed to between the Town and the owner, to correct the deficiencies discovered. The Town shall then conduct a subsequent inspection to ensure completion of the repairs.
E. 
If repairs are not properly undertaken and completed, the Town may elect to pursue enforcement as provided in § 106-25C of this chapter.
F. 
If, after an inspection by the Town, the condition of a stormwater management facility or system is determined to present an immediate danger to public health or safety because of an unsafe condition, improper construction, or poor maintenance, the Town shall take such action as may be necessary to protect the public and make the facility or system safe. Any cost incurred by the Town shall be assessed against the owner(s), as provided in § 106-25C of this chapter.
A. 
Prior to the issuance of any building permit for which stormwater management is required, the Town shall require the applicant or owner to execute an inspection and maintenance agreement in a form acceptable to the Town Attorney binding on all subsequent owners of land served by a private stormwater management facility. Such agreement shall provide for access to the facility at reasonable times for regular inspections by the Town, or its authorized representative, to ensure that the facility is maintained in proper working condition to meet design standards.
B. 
The agreement shall be recorded by the applicant and/or owner in the land records of Caroline County.
C. 
The agreement shall also provide that, if after notice by the Town to correct a violation requiring maintenance work, satisfactory corrections are not made by the owner(s) within a reasonable period of time, 30 days maximum, the Town may perform all necessary work to place the facility in proper working condition. The owner(s) of the facility shall be assessed the cost of the work and any penalties. This may be accomplished by placing a lien on the property, which may be placed on the tax bill and collected as ordinary taxes by the Town, or the Town may collect it by such other action at law as it deems appropriate.
A. 
The owner of the property that contains private stormwater management facilities installed pursuant to this chapter, or any other person or agent in control of such property, shall maintain in good condition and promptly repair and restore all ESD practices, structural stormwater management measures, grade surfaces, walls, drains, dams and structures, vegetation, erosion and sediment control measures, and other protective devices in perpetuity. Such repairs or restoration and maintenance shall be in accordance with previously approved or newly submitted plans.
B. 
A maintenance schedule shall be developed for the life of any structural stormwater management facility or ESD treatment practices and shall state the maintenance to be completed, the time period for completion, and the responsible party that will perform the maintenance. This maintenance schedule shall be printed on the approved stormwater management plan.