Upon completion of the project, but no later than two years
after completion of construction, the applicant shall submit the following
material to the Planning Board certifying that the completed project
is in accordance with the approved plans, specifications, and conditions
of the approved permit:
A. Certification by a registered professional engineer that the systems
have been installed and are functioning according to the approved
plan.
B. An as-built plan, stamped by a registered professional engineer or
land surveyor, must depict all on-site controls, both structural and
nonstructural, designed to manage stormwater associated with the completed
site, including the following information:
(2) Post-construction topography.
(3) Finished grades of all structures.
(4) Location and invert elevations of all stormwater structures.
(5) Modeled post-construction drainage area for each stormwater BMP with
pollutant removal efficiency (percent removal) based on EPA guidance
and the Massachusetts Stormwater Handbook.
(6) All structures, pavement, utilities.
(8) Deviations from the approved plan shall be noted and explanation
for the deviation provided.
C. Electronic copy of the as-built plan.
D. Documentation of compliance with all permit conditions, including
calculation of pre- and post-construction change in impervious area.
E. Maintenance surety has been submitted.
F. All inspection reports required during construction have been submitted.
G. Final operation and maintenance plan has been submitted.
H. Maintenance contracts are in place.
I. Land disturbance permit has been recorded at the Registry of Deeds.
The Planning Board's designated agent shall inspect the
system to confirm its as-built features. If the system is found to
be inadequate by virtue of physical evidence of operational defect
and/or failure, even though it was built as called for in the stormwater
management plan, it shall be corrected by the applicant before the
certificate of completion is released. If the applicant fails to act,
the Planning Board or its designated agent may use the surety bond
to complete the work.
Upon receipt and approval of the final inspection and reports
and/or upon otherwise determining that all work of the permit has
been satisfactorily completed in conformance with these regulations,
the Planning Board shall issue a letter certifying completion in conformance
with these regulations.