A. 
Sanitary sewer gravity mains and force mains.
(1) 
No gravity sewer conveying raw sewage shall be less than eight inches in diameter.
(2) 
Sanitary sewer mains shall not be installed under either curbs or sidewalks. In addition, trays, cleanouts and force main valves shall not be installed under or in concrete cement.
(3) 
No underdrains, conduits and/or cables of any nature will be installed in the same trench with sanitary sewer.
(4) 
PVC or DIP gravity sewer and force mains shall be used for all sanitary sewer except the following conditions which include, but are not limited to:
(a) 
The main is installed at a depth of less than 36 inches.
(b) 
At all stream crossings.
(c) 
The main is within 100 feet of a water supply well or below grade reservoir.
Under these conditions ductile iron pipe will be used, or as specified by the owner's Engineer.
(5) 
Sewer and water mains generally should be separated a distance of at least 10 feet horizontally. If such lateral separations are not possible, the pipes shall be in separate trenches with the sewer at least 18 inches below the water main; or such other separation as approved by the owner.
(6) 
Concrete encasement will be required for the following conditions:
(a) 
At all locations where a proposed sanitary sewer main is located closer than 10 feet to a water main (measured horizontally).
(b) 
At all crossings of sanitary sewer lines and water lines where the vertical separation is less than 18 inches.
(c) 
At all crossings of sanitary sewer lines and water lines where the sanitary sewer is vertically above the water line.
(d) 
All other locations where the vertical or horizontal separation between proposed and existing utility pipes is less than 18 inches.
(7) 
When a new sanitary line is constructed and tied into an active manhole, the new line will be plugged and remained plugged until all testing has been completed and approved by the owner.
(8) 
All sanitary sewer laterals that are scheduled for connection to a specific sewer main must be connected and extended to the curbline prior to the acceptance testing on that line.
(9) 
Neither repair clamps nor saddles are permitted to be used on new sanitary sewers within the jurisdiction of the owner. These are only to be used in cases of emergency, and then only with the prior written approval of the owner. If and when saddles are approved, they will be of the strap-on type with stainless steel hardware; no bolt-on saddles will be permitted.
(10) 
Force mains will not be tied directly into a gravity manhole. A collector manhole will be constructed adjacent to the gravity manhole and the force main will terminate in this collector manhole. The effluent will flow by gravity into the manhole, which is part of the gravity system.
(11) 
Private ejector lines shall be connected directly to the sewer main.
(12) 
Air relief valves will be required at the high points of any force main.
(13) 
Interceptors shall be provided for commercial and industrial discharges when in the opinion of the owner and/or Engineer they are necessary for the proper handling of liquid waste containing grease, oil, sand or lint to the building drainage system, the public sewer or sewage treatment plant or processes. All commercial and industrial dischargers must complete a usage questionnaire that requires submittal of plumbing plans for each facility.
B. 
Minimum grades and velocity of flow.
(1) 
All sewer shall be designed and constructed to give mean velocities, when flowing full, of not less than 2.0 feet per second, based on Kutter's Formula using an "N" value of 0.013 for ductile iron pipe or an "N" value of 0.01 for PVC pipe.
(a) 
The following are the minimum slopes that should be provided; however, slopes greater than these are desirable:
Minimum Slope in Feet per 100 Feet
Sewer Size
Ductile Iron
PVC
8-inch
0.40
0.30
10-inch
0.28
0.20
12-inch
0.22
0.15
15-inch
0.15
0.10
18-inch
0.12
0.075
21-inch
0.10
0.06
24-inch or above
0.08
0.05
(b) 
Minimum slope of mains emanating from terminal manholes shall be increased where flow conditions exist. Cul-de-sac lots shall provide minimum 0.80% slope to terminal manhole.
(2) 
Slopes slightly less than those required for the 2.0 feet per second velocity, when flowing full, may be permitted. Such decreased slopes will only be considered where the depth of flow will be 0.3 of the diameter or greater for design average flow. Whenever such decreased slopes are selected, the design engineer must furnish with his report his computations of the anticipated flow velocities of average and daily or weekly peak flow rates. The pipe diameter and slope shall be selected to obtain the greatest practical velocities to minimize settling problems.
(3) 
Sewers shall be laid with uniform slope between manholes.
(4) 
Where velocities greater than 15 feet per second are attained, special provision shall be made to protect against displacement by erosion and shock.
(5) 
The use of sewers with a slope in excess of 20% is prohibited. Instead, drop manholes should be considered. In any event, the owner and its Engineer will review all proposed sewers with a slope in excess of 20% on a case-by-case basis.
C. 
Alignment. All sewers 24 inches or less shall be laid with straight alignment between manholes. The alignment shall be checked by either using a laser beam or lamping.
D. 
Changes in pipe size. When a smaller sewer joins a larger one, the invert of the larger sewer should be lowered sufficiently to maintain the same energy gradient. An approximate method for securing these results is to place the 0.8 depth point of both sewers at the same elevation.
E. 
Manholes.
(1) 
Manholes shall be installed at the end of each line; at all changes in grades, alignment or size, and at distances not greater than 400 feet.
(2) 
A drop pipe should be provided for a sewer entering a manhole at an elevation of 24 inches or more above the manhole. Drop manholes shall be constructed with an outside drop connection. The entire outside of the drop connection shall be encased in concrete.
(3) 
The minimum diameter of manholes shall be 48 inches. A minimum access diameter of 30 inches shall be provided.
(4) 
The flow channel through manholes should be made to conform in shape and slope to that of the sewers.
(5) 
"SANITARY SEWER" shall be cast in lids of all sanitary manholes.
(6) 
All pipe penetrations into a manhole shall be no less than 90° to the center line of the downstream main.
(7) 
Manhole rims shall be set at base paving elevation and adjusted at a later date prior to installing the surface course. Manholes located in grassed areas shall be raised three inches above grade with fill built-up around the cover.
F. 
Inverted siphons (if approved by the Engineer).
(1) 
Inverted siphons should not have less than two barrels, with a minimum pipe size of six inches and shall be provided with the necessary appurtenances for convenient flushing and maintenance.
(2) 
Sufficient head shall be provided and pipe sizes selected to secure velocities of at least 3.0 feet per second for average flows.
(3) 
The inlet and outlet details shall be so arranged that the normal flow is diverted to one barrel, and that either barrel may be cut out of service for cleaning.
G. 
Laterals.
(1) 
All laterals are to be connected to the main by means of a wye connection only. The standard lateral connection will be four inches, or six inches in the case of PVC. All service laterals will be laid with the same care prescribed in § 51-12 of these specifications, which includes proper trench construction and backfill, and stoning of the trench bottom when necessary to obtain a stable base under the pipe.
(2) 
The standard sewer service lateral will be constructed of PVC, cast iron, ductile iron or a combination thereof. If the owner or builder desires to use pipe of a material other than that listed above, he must obtain the prior written approval of the owner.
(3) 
Adapters to connect the service lateral to house service lateral must be approved by the owner.
(4) 
The standard gravity sewer lateral will be constructed of four-inch diameter for all residential or six-inch diameter for commercial/industrial. Material shall be PVC SDR 35 pipe from the sewer main to the cleanout just behind the curbline.
(5) 
All sanitary sewer laterals should be installed at a grade equal to 1/4 inch per foot, but in no case will they be installed at a grade less than 1/8 inch per foot.
(6) 
All laterals will be installed at a constant grade and in a straight line. There will be a cleanout constructed and a plug provided just behind the curbline and at any point where it is necessary to change the direction of the lateral. Cleanouts are required every 50 feet on long laterals.
(7) 
When the sanitary sewer mains are over eight feet in depth, the construction of a deep cut lateral is required.
(8) 
Minimum depth for a sanitary sewer lateral is 36 inches at the curbline.
(9) 
In no case shall laterals be installed under driveways. A lateral location plan shall be submitted to the owner.
H. 
Lateral connection to existing lines.
(1) 
Gravity. Connections of the saddle type installed in the main sewer line shall be made in a smooth, round hole, machine-drilled into the top quarter of the main sewer pipe. The fitting should be such to insure that no protrusion of the fitting into the main sewer pipe shall result. The fitting shall conform to the contour of the sanitary sewer and is one that is specifically designed to fit the particular size main sewer pipe into which the connection is made. The machine-drilled hole shall be of such size to provide 1/8 space between the shoulder of the fitting and the face of the main sewer pipe when installing. All voids shall be completely filled with joint material. The joint material shall be completely waterproof and capable of withstanding the stresses normally encountered in construction or maintenance. All saddles shall be a double strapped stainless steel connection. Wrap saddle in six mil clean polyethylene and encase in minimum six inches of concrete.
(2) 
Sewage ejectors:
(a) 
Sewage ejectors discharging to an existing gravity sewer shall be provided with a check valve and shutoff valve at the location of the ejector pump. The connection to the main shall be the same as in Subsection H(1), Gravity.
(b) 
Sewage ejectors discharging to a force main shall be connected via a direct tap. Each connection shall be equipped with a check valve and shutoff valve in an at-grade box at the property line and a second check valve and shut off valve at the location of the ejector pump.
(c) 
All sewage ejector services shall be marked with plastic marking tape as described in § 51-12B(3) of the section entitled "PVC gravity sewer, pressure pipe and fittings."
I. 
Force main connection to existing force main. Sewage ejectors discharging to existing force mains shall be designed to overcome the total static and dynamic head conditions in the force main when flowing full. Connections shall be done with a tapping sleeve in accordance with manufacturer's directions.
J. 
Grease recovery units and interceptors.
(1) 
Grease recovery units (GRU) shall be installed in the waste line(s) leading from sinks, drains, or other fixtures in all food service, food processing, or other commercial establishments which produce grease/oil and which are connected into the public sewer system. Greases and oils are defined as any substance(s) with physical characteristics which enable them to be quantitatively analyzed based upon their solubility in Freon, including hydrocarbons, fatty acids, soaps, fats, waxes, oils and any other substances or materials not volatilized during solubility testing. All grease recovery units must be constructed of stainless steel or reinforced concrete. The owner shall approve the size, type, and location of each recovery unit. A sediment/solids removal unit must be installed before the grease removal unit. All installations must conform to the manufacturer's specifications and to all applicable building codes. For new construction, all grease interceptors shall be an exterior concrete unit.
(2) 
Oil, sand and lint interceptors shall be installed in the waste line(s) of all commercial establishments which produce such waste and are connected into the owner's sewer system.
(3) 
All grease recovery units or interceptors shall be so installed as to provide ready accessibility to the cover and contents thereof, for servicing and maintaining the grease recovery units or interceptors in working operating condition. All grease recovery units or interceptors shall be maintained in an efficient operating condition by regular, periodic removal of accumulated contents.
(4) 
The owner, through its authorized officers, employees and agents, shall have authority to inspect, at reasonable times, those food service, food processing or other commercial establishments which produce oil, grease, sand, lint or other harmful ingredients and which are connected into the owner's sewer system to ensure that said establishments which produce oil, grease, and are properly maintaining their grease recovery unit and/or interceptor on all waste line(s).
(5) 
Plumbing and floor plans shall be submitted for owner review and approval. Finalized plans shall be forwarded by the establishment to the owner for their records.
(6) 
Full service restaurants, pizzerias and fast food type restaurants or other commercial establishments which produce excessive quantities of grease/oily waste shall furnish both an interior GRU and an exterior grease trap.
(7) 
Grease conveying laterals shall be separated from laterals conveying raw sewage until after interceptor connection.
K. 
Prior to construction. Prior to starting construction of a sewer system within the Township, the developer or owner must have in his possession a set of owner-approved drawings. In addition, he must have paid all the necessary charges and fees as well as obtaining the necessary bonding. When easements are necessary, all paperwork must be in order; and if road-opening permits are required, these must also be obtained before work can begin.
A. 
Description. PVC gravity sewer and pressure pipe for proposed sanitary sewer system.
B. 
Materials.
(1) 
PVC gravity sewer pipe and fittings:
(a) 
ASTM D-3034; SDR 35; sizes four-inch through fifteen-inch.
(b) 
ASTM F-679; sizes eighteen-inch through twenty-seven-inch.
(c) 
ASTM F-794; sizes eighteen-inch through forty-eight-inch ribbed.
[1] 
Joint design: ASTM D-3212, Push-on-type joint using an elastomeric ring gasket. Infiltration shall not exceed 50 gallons/inch diameter/mile/day.
[2] 
Joint material: elastomeric ring rubber gasket, ASTM D-3212.
[3] 
Joint material primer/adhesive: as provided or specified by pipe manufacturer.
(2) 
PVC pressure sewer pipe and fittings:
(a) 
AWWA C900; sizes four-inch through 12 inches.
[1] 
Coupling shall be an integral part of pipe.
[2] 
Pipe shall have slip-on joints with a rubber ring seal.
[3] 
Pipe shall be PVC "Blue Brute" pipe with "Ring-Tite" joints as manufactured by Johns-Manville, or approved equivalent.
[4] 
Pipe shall be of the following pressure classes, having the SDR numbers indicated.
[a] 
DR-14, Pressure Class 200.
[b] 
DR-18, Pressure Class 150.
[c] 
DR-25, Pressure Class 100.
[5] 
Fittings and rubber rings shall be as supplied by the pipe manufacturer.
(3) 
Locator wire.
(a) 
Locator wire shall be minimum No. 9 AWG suitable for direct burial rated at 600 VAC.
(b) 
Locator wire shall be placed on the top side of the HDPE pipe. Wire shall be attached to the pipe using nylon cable ties spaced at ten-foot intervals.
(c) 
Locator wire shall be continuous along entire length of pipe. Heat shrink splice kits shall be used where wire sections need to be spliced.
(d) 
Locator wire ends shall be terminated at the valve box and curb stop pit using a copper set screw lug attached to the valve box and the curb stop pit.
C. 
Methods of construction.
(1) 
Reference standard used in this specification section:
(a) 
American Society for Testing and Materials (ASTM):
[1] 
ASTM D-3034: Type PSM Polyvinyl Chloride (PVC) Sewer Pipe and Fittings.
[2] 
ASTM F-679: PVC Large Diameter Plastic Gravity Sewer Pipe and Fittings.
[3] 
ASTM F-794: PVC Large Diameter Ribbed Gravity Sewer Pipe and Fittings.
[4] 
ASTM D-3212: Joint for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals.
[5] 
ASTM D-2241: PVC Plastic Pipe.
(b) 
American Association of State Highway and Transportation Officials:
[1] 
M-45: Aggregate for Masonry Mortar.
(c) 
New Jersey Department of Transportation, Standard Specifications for Road and Bridge Construction 1980 Supplement.
(2) 
Submittals:
(a) 
Manufacturer's literature and recommendations:
[1] 
Submit manufacturer's descriptive literature for all materials to be used.
[2] 
Submit pipe manufacturer's recommended method of gasket installation.
[3] 
Submit all test results including a diagram of sections tested.
[4] 
Submit all of the above for owner Engineer's approval.
(b) 
Certificates:
[1] 
Submit manufacturer's certified letter stating that pipe or joint material ordered meets requirements of this specification. Letter shall indicate compliance with appropriate ASTM designations listed.
[2] 
Submit two copies prior to installing materials.
(3) 
Product delivery, storage and handling:
(a) 
Storage of materials:
[1] 
Store materials to prevent physical damage.
[2] 
Store pipe and fittings off ground to prevent dirt and debris from entering.
[3] 
Store flexible gasket materials and joint primer or adhesive compounds in cool dry place. Keep rubber gaskets clean, away from oil, grease, excessive heat, and out of direct rays of sun.
(b) 
Handling of materials:
[1] 
Protect materials during transportation and installation to avoid physical damage.
[2] 
Use extra care in cold weather when flexibility and impact resistance of PVC pipe is reduced.
[3] 
Do not install out-of-round pipe.
[4] 
Unload pipe to prevent abrasion.
[5] 
Do not drag or push pipe when handling or distributing on project site.
(4) 
Inspection by contractor:
(a) 
Check pipe for following information which shall be clearly marked on each pipe section:
[1] 
Pipe type and SDR number.
[2] 
Nominal pipe size.
[3] 
The PVC cell classification; for example, 12454-B.
[4] 
Name or trademark of manufacturer.
[5] 
The ASTM specification designation.
(b) 
Check fittings for the following markings:
[1] 
The ASTM specification designation.
[2] 
Manufacturer's name or trademark.
[3] 
Nominal size.
[4] 
The material designation PVC, PSM.
(c) 
Inspect pipe for defects prior to placement in trench. The pipe and fittings shall be free from visible cracks, holes, foreign inclusions or other injurious defects.
(d) 
Assure that all materials are to the type specified and are not defective. Unmarked pipe; or pipe and materials not meeting specifications requirements shall be removed from the site as directed by the Engineer.
(5) 
Excavation for trenches:
(a) 
Dig trenches to the uniform width required for the particular item to be installed, sufficiently wide to provide ample working room.
[1] 
Maximum trench width to a point one foot above the outside top of pipe shall be the pipe outer diameter plus 16 inches.
[2] 
Maximum trench width at ground surface shall be as required for depth of pipe.
(b) 
Excavate trenches to the depth indicated or required. Carry the depth of trenches for piping to establish the indicated flow lines and invert elevations.
(c) 
Trenches for pipes shall not be opened more than the number of linear feet of pipe that can be placed and backfilled in one day.
(d) 
Grub roots and stumps within six inches of outside surface of pipe bottom and sides to minimum depth of six inches below bottom of trench.
(e) 
Install pipe bedding of material approved for initial backfill in accordance with the standard details and as specified herein.
(6) 
Installation:
(a) 
Lay pipe only in presence of Engineer, Engineer may order removal and relaying of pipe not so laid.
(b) 
Fine grade trench bottom so that pipe is supported for its full length.
(c) 
Lay pipe to lines and grades required. Face socket end of pipe in direction of pipe laying.
(d) 
Do not lay pipe on unsuitable material, in wet trench, or in same trench with another pipe or utility.
(e) 
Lower pipe into trench with ropes, machinery, or other means approved by Engineer.
(f) 
General procedure for joining pipe:
[1] 
Do not use excavating equipment to shove pipe sections together.
[2] 
Hold pipe securely and in proper alignment when joining.
[3] 
Do not disturb previously made joints. Check completed piping to assure joints are intact. Ensure placement of backfill over pipe is accomplished without disturbing pipe position.
[4] 
Do not allow earth, stones, or other debris to enter pipe or fittings.
[5] 
Method of installing joint materials and joining piping shall be in strict accordance with manufacturer's printed instructions as approved by the Engineer.
(7) 
Backfill and compaction:
(a) 
Initial backfill:
[1] 
Initial backfill material shall be soil aggregate designation I-8 conforming to the requirements of Article 8.8.1. Table 36 of the Standard Specifications, 1980 Supplement, or stone crushing to conform with AASHTO designation M-43 (ASTM designation D448), Size No. 8, 1/8 inch to 3/8 inch (2.36 mm to 9.25 mm) clean, free flowing and shall meet all ASTM C-33 requirements for quality and soundness.
[2] 
Install initial backfill material as shown on the standard details for the type of pipe being used.
[3] 
When required material shall be placed under the pipe haunch to provide adequate side support. Material shall be installed entire trench width and shall be tamped and rodded to ensure full contact with pipe at haunch up to the spring line.
[4] 
Little or no tamping of the initial backfill directly over the pipe shall be done.
(b) 
Final backfill: See § 51-8, Trench excavating, backfilling and compacting, of Article II, General Specifications..
(8) 
Testing:
(a) 
Deflection testing:
[1] 
For pipe conforming to the requirements of ASTM D3034, maximum allowable pipe deflection (reduction in vertical inside diameter) shall be 7 1/2%.
[2] 
For pipe conforming to the requirements of ASTM D2241, maximum allowable pipe deflection (reduction in vertical inside diameter) shall be 5%.
[3] 
Deflection tests shall be successfully performed on the complete installation by means of one of the following methods prior to the acceptance of construction.
[a] 
"Go-No-Go" mandrel properly sized.
[b] 
Calibrated television.
(b) 
Lamping:
[1] 
Engineer will lamp all installed pipe between manholes. Sewer lines shall meet the following standards to pass the lamping inspection.
[a] 
Barrel of pipe shall have no vertical deflection (not to be confused with the deflection test), and at least 75% of barrel shall be visible in the horizontal direction.
[b] 
Pipe not meeting this specification shall be relaid and relamped until compliance is achieved, at no cost to the owner.
(c) 
Air testing:
[1] 
Air testing shall conform to the requirements of § 51-17, Testing sanitary sewer force mains, except as herein modified.
[2] 
The minimum time duration for a low-pressure exfiltration pressure drop between two consecutive manholes shall not be less than shown in Table 1.
[3] 
The prescribed drop shall not exceed 0.5 psi from 3.5 to 3.0 psi in excess of the groundwater pressure above the top of the sewer.
Table I
Minimum Duration For Air Test Pressure Drop
Pipe Size
Time
(minutes)
Inches
Millimeters
4
100
2 1/2
6
150
4
8
200
5
10
225
6 1/2
12
305
7 1/2
15
380
9 1/2
(9) 
Appurtenance installation:
(a) 
Manholes:
[1] 
Precast manholes with connection ports shall have elastomeric seals precast into manhole walls.
[2] 
Precast manholes with connection ports shall have flexible boot or sleeve precast into manhole walls.
(b) 
Laterals. All laterals shall be installed with the same construction procedure as the sewer main.
A. 
Description. Provide ductile iron pipe for sanitary sewer force main or for gravity sanitary sewer main.
B. 
Materials.
(1) 
Sanitary sewer force main:
(a) 
Ductile iron pipe:
[1] 
Shall conform to AWWA C151.
[2] 
Manufactured in eighteen-foot or twenty-foot nominal lengths.
[3] 
Pressure Class 150 (minimum).
(b) 
Joints for ductile iron pipe: push-on joint, conforming to AWWA C151 and AWWA C111.
(c) 
Pipe fittings:
[1] 
Shall be ductile iron fittings conforming to AWWA C110, with a minimum pressure rating of 250 psi.
[2] 
Fitting shall have push-on-type joints.
(d) 
Plugs and clamps. Plugs shall be solid plugs conforming to the pipe sizes indicated on the plans, and shall be Plug No. F-1147 as manufactured by Clow Corporation, or approved equal. Clamps for retaining plugs shall be Socket Clamp No. F-740, as manufactured by Clow Corporation, or approved equal.
(e) 
Gasket lubricant:
[1] 
Water-soluble and not having deteriorating effects on the pipe or rubber gaskets.
[2] 
Shall be as supplied by pipe manufacturer or as approved by the Engineer.
(2) 
Sanitary sewer gravity main:
(a) 
Ductile iron pipe:
[1] 
Shall conform to AWWA C151.
[2] 
Manufactured in eighteen-foot or twenty-foot nominal lengths.
[3] 
Pressure Class 150 (minimum).
(b) 
Joints for ductile iron pipe: push-on joint, conforming to AWWA C151 and AWWA C111.
(c) 
Pipe fittings:
[1] 
Shall be ductile iron fittings conforming to AWWA C110, with a minimum pressure rating of 250 psi.
[2] 
Fittings shall have push-on-type joints.
(d) 
Plugs and clamps: Plugs shall be solid plugs conforming to the pipe sizes indicated on the plans, and shall be Plug No. F-1147 as manufactured by Clow Corporation, or approved equal. Clamps for retaining plugs shall be Socket Clamp No. F-740, as manufactured by Clow Corporation, or approved equal.
(e) 
Gasket lubricant:
[1] 
Water-soluble and not having deteriorating effects on the pipe or rubber gaskets.
[2] 
Shall be as supplied by pipe manufacturer or as approved by the Engineer.
C. 
Methods of construction.
(1) 
Submittals:
(a) 
All pipe and fittings shall be inspected and tested at place of manufacture as required by the AWWA standards referenced in this specification. Provide Engineer with two copies of certifications from each manufacturer stating the product was inspected as required, and that the test results comply with the AWWA standards.
(b) 
Submit manufacturers' product data for pipe, fittings, and gaskets as specified in § 51-5, Product data, of Article II, General Specifications.
(c) 
All manufacturers shall validate other than by certification the ductility of each length of pipe by an Underwriters Laboratory approved method. All ductile iron pipe is to have Underwriters Laboratory approval.
(d) 
Submit all test results, including a diagram of sections tested.
(2) 
Inspection and quality of pipe:
(a) 
Before being lowered into the trench, each pipe shall be carefully inspected, and those not meeting the specifications shall be rejected and either destroyed or removed from the work within 10 hours. No pipe shall be laid except in the presence of the Engineer or his authorized inspector. The Engineer may order the removal and relaying of any pipe not so laid.
(b) 
In addition to the inspection made by the Engineer, the contractor shall carefully examine all pipe and special castings before placing the same in the trench. Any pieces which are broken or show evidence of cracks or fractures shall be rejected by him. Such inspection shall carry with it the responsibility on the part of the contractor for the removal at his own expense of all pipe, special castings, and appurtenances, incorporated in the work, and which under test are found to be cracked or otherwise defective.
(3) 
Installation of pipe and fittings:
(a) 
Excavation and backfill for pipes shall conform to § 51-8, Trench excavating, backfilling and compacting.
(b) 
All piping shall be installed in a neat and workmanlike manner. All piping shall be installed to accurate lines and grades and shall be supported as shown in the standard details, specified, or necessary. Where temporary supports are used, they shall be sufficiently rigid to prevent shifting or distortion of the pipe. Suitable provision shall be made for expansion where necessary.
(c) 
No defective pipe or fitting shall be laid or placed in the piping, and any piece discovered to be defective after having been laid shall be removed and replaced by a sound and satisfactory piece by the contractor.
(d) 
Every pipe and fitting shall be cleared of all dirt and other debris before being installed and shall be kept clean until accepted in the completed work.
(e) 
No pipes shall be laid in fill or other unstable material, in wet trench, or in same trench with another pipe or other utility. A minimum eighteen-inch clearance shall be maintained between the outside surface of pipe and outside surface of other existing pipes and structures. When this clearance cannot be maintained, contact the Engineer for instructions prior to proceeding with the pipe installation.
(f) 
No direct contact between pipes and structures at crossings will be permitted. Pipes in place shall not be worked over or walked on until covered by layers of earth well tamped in place to a depth of 12 inches over the pipe.
(g) 
Minimum cover over sewer mains shall be four feet.
(h) 
The interior of all pipes shall be thoroughly cleaned of all foreign material before being lowered into trench. Pipes shall be kept clean during laying operations by means of plugs or other approved methods.
(i) 
Brace all plugs as required to prevent leakage or blowout during testing.
(4) 
Piping supports for ductile iron force mains. The contractor shall furnish and install all supports necessary to hold the piping and appurtenances in firm, substantial manner at the lines and grades required. Where required, bends, tees, and other fittings buried in the ground shall be backed up with concrete placed against undisturbed earth where firm support can be obtained. If the soil does not provide firm support, then suitable bridle rods, clamps, and accessories to brace the fitting properly shall be provided. Such bridle rods, etc., shall be coated thoroughly with an approved bituminous paint after assembly or, if necessary, before assembly. This work shall include bracing plugs to prevent leakage or blowout during testing.
(5) 
Handling and cutting pipe. Every care shall be taken in the handling and laying of pipe and fittings to avoid damage to the pipe, scratching or marring machined surfaces, and abrasion of the coating or lining. Pipe cuts shall be made using an abrasive wheel, rotary wheel cutter, guillotine pipe saw, milling wheel saw, oxyacetylene torch or other method approved by the Engineer. Ground cut ends and rough edges smooth. For push-on connections, bevel all cut ends.
(6) 
Assembling piping.
(a) 
Clean ring groove and bell socket prior to inserting rubber gasket scal. Properly seat gasket; make sure it faces proper direction.
(b) 
Clean and lubricate spigot end of pipe. Lubricate spigot end of pipe and rubber gasket.
(c) 
Hold pipe securely and in proper alignment when joining.
(d) 
Join pipe so that reference mark on spigot end, if provided by manufacturer, is flush with end of bell.
(e) 
Join pipe in strict accordance with manufacturer's printed installation procedures.
(7) 
Protection of work:
(a) 
Great care shall be exercised in the protection of finished work. Joints once made and disturbed shall be subjected to immediate rejection. It shall, therefore, be the duty of the contractor to avoid the slightest movement in completed work, while in the act of laying the pipe, in backfilling, or in the passage of workmen up and down the trench. At all times during which pipe is not laid, the end of the pipe shall be sealed with a tight-fitting plug. In no case will the drainage of trench water through a complete pipe be permitted.
(b) 
All curves, bends, tees, hydrants or ends of pipe shall be securely blocked with socket clamps or yokes to prevent movement. At the end of line or turn, where provision has been made for future extension or connection, fittings shall be furnished with lugs and anchored by means of socket clamps or yokes.
(8) 
Adapters. When it is necessary to join pipes of different types the contractor shall furnish and install the necessary adapters. Adapters shall have ends conforming to the above specifications for the appropriate type of joint to receive the adjoining pipe. When adapters join two classes of pipe, the bodies may be of the lighter class.
(9) 
Pipe repairs shall be accomplished utilizing stainless steel double banded repair clamps (Rockwell 226 "Super Reach" or equal), installed in accordance with the manufacturer's printed instructions.
A. 
Description.
(1) 
Provide precast concrete manholes for gravity sanitary sewer system.
(2) 
Reconstruct existing manholes.
(3) 
Provide connection to existing manholes.
B. 
Materials.
(1) 
Precast concrete manholes shall conform to ASTM C 478.
(2) 
Rubber gasket for precast manhole sections shall conform to ASTM C 361. Concrete and rubber gasket joint shall be watertight at head pressure of up to 50 feet.
(3) 
Rubber gasket pipe to manhole seal for precast manholes: ASTM C 443.
(a) 
Gasket shall be cast integrally in manhole wall.
(b) 
Use "A-Lok" gasket as manufactured by Atlantic Concrete Products Company, Omega Concrete Products, Inc., Duncan Thecker Precast, or approved equal.
(4) 
Ladder rungs. Shall be aluminum alloy conforming to ASTM C478.
(a) 
Steps shall be 12 inches wide with a nonslip surface, with the ends turned up a minimum of two inches. Rungs shall be set into the wall a minimum of three inches, and extend six inches from the manhole wall.
(5) 
Castings for manholes. Campbell Foundry Pattern No. 1012D with lifting handles and pick holes and "SANITARY SEWER" cast in lid, or approved equal.
C. 
Methods of construction.
(1) 
Submittals. Submit manufacturers' product data for ladder rungs and precast manholes as specified § 51-5, Product data, of Article II, General Specification
(2) 
Reference standards used in this specification:
(a) 
New Jersey State Highway Department Standard Specifications:
Section 603: Inlets and Manholes.
(b) 
American Society for Testing and Materials (ASTM):
[1] 
ASTM C361. Reinforced concrete low-head pressure pipe.
[2] 
ASTM C443: Joints for Circular Concrete Sewer and Culvert Pipe Using Rubber Gaskets.
[3] 
ASTM C478: Precast Reinforced concrete manhole sections.
(3) 
The general method of construction and manhole reconstruction shall conform to Section 603 of the Standard Specifications. The manhole shall be constructed as shown on the standard details.
(4) 
Manhole walls shall be constructed of precast concrete rings and all joints between. The outside surface shall be painted with seal coats of coal tar or asphalt. Manhole walls may be constructed of poured concrete, subject to approval by the owner's Engineer. Installation of rubber gaskets for precast manholes shall be in accordance with the manufacturers' recommendations.
(5) 
Frames shall be well bedded in mortar, making a watertight joint. Cover and frame shall have a shop coat of asphaltic pitch and shall have a field coat of similar paint after the frame is set in the final position. Steps shall be provided in the manhole as shown on the standard details.
(6) 
Each manhole shall be constructed absolutely watertight. Manholes that are not watertight will not be accepted. Plastering on top of defective joints to correct leaky conditions will not be permitted.
(7) 
The invert channels shall be smooth and semicircular in shape conforming to the inside of the adjacent sewer section. Changes in direction of flow shall be made with a smooth curve of as large a radius as the size of the manhole will permit. Changes in size and grade of the channels shall be made gradually and evenly. The invert channels shall be formed in the concrete fill above the manhole base, or shall be half tile laid in concrete, or shall be constructed by laying full section sewer pipe through the manhole and cutting out the top half after the surrounding concrete has hardened. The floor of the manhole outside the channels shall be smooth and shall slope toward the channels not less than one inch per foot nor more than two inches per foot.
(8) 
Construct manholes to the lines and grades required in the system being installed.
(9) 
A maximum of four courses of brick, up to 12 inches in height, shall be used on any precast manhole. When a greater number of courses are required to attain the proper grade, another precast section shall be used.
(10) 
Provide all manhole top sections with minimum thirty-two-inch diameter clear opening.
A. 
Description.
(1) 
Design, furnish, install, test and monitor complete sanitary sewage pumping station if required by project conditions.
(2) 
Sewage pumping stations shall be of the wet well type with submersible pumps.
B. 
Submittals.
(1) 
Prior to pump station approval, the applicant shall submit eight copies of the following for approval:
(a) 
Engineer's design report for the pump station including flow and head calculations for the pump station and common force main.
(b) 
Design drawings and specifications.
(2) 
Prior to construction, the contractor shall submit shop drawings for the pump station in accordance with § 51-5, Product Data, of Article II, General Specification.
(3) 
Before testing and startup, 10 copies of complete pump station O&M manuals shall be submitted to the owner/Engineer for review and approval.
(4) 
As-built plans shall be submitted to the owner/Engineer prior to the release of the performance bond.
C. 
Pumps.
(1) 
Pumping station capacity should be compatible with the ultimate capacity of the influent sewer. At least two pumps, each designed to handle peak flows for ten years hence, shall be provided. If more than two pumps are provided, their capacities shall be such that, upon failure of the largest pump, the others will handle such peak flows. Pumps shall include run-hour meters on the main electrical panels.
(2) 
Special repair tools and accessories as well as 10 copies of all operation and maintenance literature required for maintenance shall be provided.
D. 
Wet wells.
(1) 
The capacity of a wet well should not exceed 10 minutes retention when flow is at the average dry weather rate.
(2) 
The floors of wet wells shall slope at least 45° toward pump suctions to prevent solids accumulation.
(3) 
Wet wells shall be designed and installed to comply with OSHA regulations and the requirements governing confined space entry.
E. 
Electrical equipment.
(1) 
All control equipment and standby generator shall be located outside of the wet well in a suitable building, approved by the owner.
(2) 
Automatic visual and audible alarm systems shall be provided for all pumping stations operating independently of the station power. The alarm shall be activated in cases of power failure, pump failure, level control failure, or any cause of pump station malfunction. Pump station alarms shall be telemetered, including identification of the alarm condition to the sewage treatment plant or other location as designated by the owner.
(3) 
Ground fault interrupter (GFI) breakers shall be provided for all dry well and exterior fixtures.
(4) 
All electrical equipment and work shall comply with Fire Underwriter's regulations for the location involved, the National Electric Code, and OSHA 1910.147.3.C.2.
(5) 
All outdoor panels and junction boxes shall be NEMA 4X 316 stainless steel.
F. 
Emergency power.
(1) 
An emergency power source must be provided with automatic transfer capability in case of primary power failure. This unit must be sized so as to provide all power necessary to supply all the electrical equipment for the pumping station from the period of primary power failure.
(2) 
The owner shall be supplied with 10 sets of operational instructions, including emergency procedures and maintenance schedules. Any special tools and spare parts as designated by the owner shall also be provided.
G. 
Pumping stations - general.
(1) 
Unless otherwise approved by the owner, pump stations shall be underground concrete wet well type.
(2) 
The owner shall be contacted prior to the selection of any pump and/or pump station within the owner's service area.
(3) 
Pumps and pumping stations shall be provided for transfer of raw sewage when flow by gravity is not possible or impractical, as determined by the owner/Engineer.
(4) 
Raw sewage shall be screened before pumping unless special pumping equipment approved by the owner is used. A trash basket and guide rails, constructed of either aluminum or stainless steel, must be provided in the wet well. A mechanical means, such as a winch, must be provided so this basket can be removed from the wet well for cleaning.
(5) 
Wet wells shall be provided with adequate light and ventilation and a means of access for pumps and trash basket.
(6) 
At least two pumps shall be provided at each pump station. All pumps shall be designed for at least 2.5 times the expected average daily flow for 10 years hence. Pumps shall be designed to overcome the total static and ultimate dynamic head conditions of any common force main flowing full. At the owner's discretion, variable frequency drives (VFD) may be required for any new or rehabilitated pump station. VFD shall be Safetronics or equal.
(a) 
Two-pump system:
[1] 
One pump shall be considered a standby for the other.
[2] 
Both pumps shall be the same capacity.
[3] 
The pump considered to be the lead pump shall be alternated on each lead pump startup.
(b) 
Three-pump system:
[1] 
The pumps shall be of such capacity that with any one pump out of service, the remaining pumps shall have the capacity to handle the expected maximum flow.
[2] 
Provisions shall also be included for all the pumps to operate in parallel, should the level in the wet well continue to rise above the starting level for the lead pump.
(7) 
Pumps shall be capacity of passing spheres of at least three inches in diameter, and pump suction and discharge piping shall be at least four inches in diameter.
(8) 
Pump stations shall be located outside the FEMA 100-year flood area and shall not be subject to flooding. Pump stations shall be accessible by motor vehicles at all times.
(9) 
Pump controller.
(a) 
Controller.
[1] 
The PLC should be a Modicon Momentum series with the following devices:
Processor
171CCC76010
TOD
Option Adapter
I/O Base 1
ANR 120-90
I/O Base 2
ADM 350-10
Com. Adapter
170INT 11000
[2] 
Programming for the PLC with Concept - Version 2.6 for a complete working duplex pump control.
[3] 
Duplex pump control for VFD/bypass operation with all required programming to accommodate items listed in HMI control paragraph.
[4] 
The level control system should have a Pressure System, Incorporated's submersible transducer, a 700 series with a 0-5V input to PLC.
[5] 
Separate independent relay logic, controlled by Warrick float balls, should be selector switch enabled to provide backup automatic level control to the bypass starters during the event of PLC or HMI failure. This selector switch shall disable PLC operation.
[6] 
Riverside Sewerage Authority shall be provided with complete PLC and HMI Software licenses, written programs in electronic and paper format and PC to device cables.
[7] 
The HMI interface will be a Red Lion - G308 color touch screen. Operator programming for the G308 is free software, downloadable from Red Lion's wet site (Crimson 2.0). Screens developed should include the following:
[a] 
Wet well level - graphical and digital readout.
[b] 
Set point control.
[c] 
Pump hand off auto control.
[d] 
Pump hours.
[e] 
Pump hours reset.
[f] 
Manual speed control and time out.
[g] 
Wet well pump level set point adjustment.
[h] 
Pump alternation control:
[i] 
Manual control.
[ii] 
Cycle control.
[iii] 
Timed control.
[i] 
Alarm page for:
[i] 
Wet well flooded.
[ii] 
Wet well low level.
[iii] 
Pump failure.
[j] 
VFD/bypass control selection.
[k] 
PID control function.
[l] 
Alarm history.
(b) 
Automatic pump alternation. Upon operator selection, the controller shall select first one pump then the second pump, to run as the lead pump for a pumping cycle. Alternation of the lag pump shall occur similarly. All alternations shall occur at the end of a pumping cycle. In triplex configuration, all pumps should cycle.
(c) 
Transducer. The transducer shall be permanently mounted in the wet well to accurately measure the liquid level in the wet well. The output signal shall be proportional to the liquid level from 0% to 100%, plus or minus 1%. The sensor shall be capable of operating ranges of one to 25 feet, and shall function over an ambient temperature range of -40° F. to 200° F. and shall be rated FAM and CAS for Class I and Class II hazardous environment.
(d) 
Installation. The transducer shall be installed in a stilling well constructed of three-inch diameter PVC conduit that will extend through the top slab of the wet well. The cable outside the wet well shall be enclosed in seal-tite conduit and supported with a unistrut support as shown on the plan. Link seals shall be used at wet well penetrations.
(e) 
Warranty. The manufacturer of the controller shall guarantee for one year of operation, that the equipment shall be free from defects in design, workmanship or materials. In the event a component fails to perform as specified or is proven to be defective in service during the guarantee period, the manufacturer shall promptly replace the defective part at no cost to the owner.
(10) 
Provide minimum 2,000-pound capacity winch with a 2.85 to 1 cranking ratio. Winch shall be the ratchet type with a disc brake. Winch shall be supported by a removable, swiveling-type davit. Winch cable shall be minimum three-sixteenths-inch diameter stainless steel and have sufficient length to reach the bottom of the wet well. The end of the cable shall be furnished with a spring-loaded hook.
(11) 
Alarm dialer.
(a) 
An automatic alarm dialer shall be provided in the location described. The alarm dialer shall be mounted and wired within the control enclosure with the dialer's keypad and display mounted through the enclosure door. The dialer shall be a solid state component capable of storing and dialing up to 16 phone numbers, each up to 32 digits in length. The dialer shall be a sixteen-channel device, wired for the following alarm inputs:
[1] 
System failure.
[2] 
High water level alarm.
[3] 
Generator status.
[4] 
Generator failure.
[5] 
Control power failure (integral to dialer).
[6] 
Station temperature (integral to dialer).
[7] 
Low water level alarm.
[8] 
Pump No. 1 failure (high temperature, overload, pump failure).
[9] 
Pump No. 2 failure (high temperature, overload, pump failure).
(b) 
The dialer shall utilize digital speech recording. The dialer shall allow the user to record and rerecord in their own voice messages for each input channel and for the station ID. The time for each message shall be adjustable, and recordings may be made at the front panel or from any remote touch tone telephone. The dialer shall be Verbatim Raco Model VSS.
(12) 
Pump station design shall comply with all Occupational Safety and Health Standards (OSHA), including Section 1910.27 for minimum dimensions of access hatch openings.
(13) 
The pump station design shall include a complete analysis of buoyant forces. In addition, structural design calculations for all concrete structures and metal support system shall be submitted.
(14) 
Provide minimum of eight copies of all shop drawings to the owner/Engineer prior to manufacture for review.
(15) 
The pump station operation and maintenance manual shall include at a minimum, but not be limited to, the following information:
(a) 
Certified pump curves from the actual pumps being furnished.
(b) 
Suggested maintenance schedule.
(c) 
Complete and detailed schematics of all electrical systems and controls, including schematic and wiring diagrams for the engine alternator set, automatic transfer switch and interconnecting diagram showing connections to individual components which constitute the standby power system.
(d) 
Complete and detailed exploded view drawings of all equipment included with the pump station.
(e) 
Descriptions of and operating instructions for each major component of the pump control as supplied.
(f) 
Instructions for operation of the pump controls in all intended modes of operation.
(g) 
Instructions for the adjustment, calibration, and testing of selected electronic components or assemblies, normally considered replaceable by the manufacturer, whose performance is not ascertainable by visual inspection.
(16) 
The owner's Engineer shall be present for on-site testing of all equipment, including, but not limited to, determining pump capacity. The pump station manufacturer's representative shall perform the testing.
(17) 
The applicant shall coordinate progress of the work with utilities and local authorities which require inspection and approval of the work.
(18) 
The pump station and generator manufacturers shall each provide the services of a factory trained representative for a minimum period of eight hours to perform initial startup of the pump station and generator, and to instruct the owner's operating personnel in the operation and maintenance of the equipment. This instructions time is in addition to any required testing and equipment startup preparation.
(19) 
All aluminum materials shall be suitably protected against dissimilar materials, such as concrete, steel, nonferrous metals, etc., using neoprene washers, painting or other approved method.
(20) 
The owner shall be provided with special repair tools, spare parts and accessories for each pump station.
(21) 
In addition to the above criteria, all pump stations shall meet the New Jersey Department of Environmental Protection Rules and Regulations for the Preparation and Submission of Plans for Sewer Systems and Wastewater Treatment Plants.
H. 
Wet well.
(1) 
Minimum wet well diameter shall be seven feet. Top of wet well slab shall be minimum nine inches above the finished grade.
(2) 
The concrete wet well construction shall conform to:
(a) 
ASTM C478, Precast Reinforced Concrete Manhole Sections.
(b) 
ASTM C890, Minimum Structural Design Loading for Monolithic or Sectional Precast Concrete Water and Wastewater Structures.
(c) 
ASTM C913, Precast Concrete Water and Wastewater Structures.
(d) 
ASTM C443, Joints for Circular Concrete Sewer and Culvert Pipe, Using Rubber Gaskets (for joint design only).
(e) 
ASTM C923, Resilient Connectors between Reinforced Concrete Manhole Structures and Pipes.
(3) 
There shall be no joints between the base slab and first riser section, as these two sections shall be monolithically constructed.
(4) 
The floors of wet wells shall slope at least 45° toward pump suctions to prevent solids accumulation.
(5) 
Provide aluminum bar screen basket with aluminum guides, constructed of aluminum alloy 6061-T6 or 6063-T6. All raw sewage shall be screened before pumping unless special pumping equipment approved by the owner is utilized. Provide removable bar screen basket with guide rails constructed of aluminum alloy 6061-T6 or 6063-T6. Minimum 3/16 inches by 1 1/4 inches aluminum flat bars shall be positioned on the bottom and all sides. Maximum clear space between bars shall be one inch. All hardware shall be stainless steel.
(6) 
Provide access hatches based on the following requirements:
(a) 
One access hatch shall be provided to accommodate removal of the bar screen and for personnel access. Hatch size shall be as large as can be structurally accommodated in the wet well top slab. Minimum hatch width shall be 30 inches.
(b) 
Each hatch shall be equipped with heavy duty hinges, lifting handle, spring operators, automatic hold open arm with release handle, and a snap lock with removable handle, all of stainless steel. In addition, all hardware shall be stainless steel.
(c) 
Two heavy-duty stainless steel safety chains shall be provided on each end of all double leaf doors.
(d) 
The hatch covers shall be mill finished.
(e) 
All metal used in fabricating the access doors shall be either aluminum or stainless steel. All aluminum shall be alloy 6061-T6 or 6063-T6 and all stainless steel shall be Type 316.
(f) 
Each hatch shall be provided with an integral safety gate that provides fall-through protection.
(7) 
Provide an exhaust air odor control system:
(a) 
Capacity minimum of 12 air changes per hour.
(b) 
Unit to be Carbtrol Model G Series air purification system.
(c) 
Motor shall be 115/230 VAC single phase, 3,400 rpm, with manual starter.
(d) 
Suction piping material to be PVC. Final connection to unit shall be hose supplied with system.
(e) 
PVC ball valve shall be supplied on suction side of unit for flow control.
(f) 
Provisions for manual operation only shall be provided. On/off switch shall be located in the control room.
(g) 
Applicant's engineer to specify blower capacity and static pressure, and provide backup calculations.
(8) 
On the entire interior concrete surface of the wet well, provide an epoxypolyamide or approved equal painting system installed in accordance with the painting system manufacturer's recommendations (see Section 5.9.X.).[1]
[1]
Editor's Note: So in original.
(9) 
All materials inside the wet well shall be aluminum alloy 6061-T6, 6063-T5 or 6063-T6, Type 316 stainless steel, PVC or fiberglass. This includes the fall prevention system, expansion anchors, anchor bolts, nuts and washers.
I. 
Standby emergency power engine/generator.
(1) 
General. The contractor shall furnish and install a complete diesel engine/generator set, complete, at the job site. The generator set shall be installed inside the control building. The complete standby system shall consist of:
(a) 
A diesel engine/generator set to provide standby electric power during periods of failure of normal utility power supply. The engine/generator capacity shall be selected on the following basis:
[1] 
Engine/generator set capacity shall be sized assuming raw sewage pumps operating with motors sized to drive pumps installed with largest pump impeller required for all future flows and all future total dynamic head conditions.
[2] 
Starting. Unit shall be capable of simultaneously starting all raw sewage pumps required to handle the average daily flow, and a minimum accessory load of 6.5 KW due to auxiliary equipment and the wet well light and blowers. Any additional loads for items such as exterior lights shall also be included. A time delay device shall be used to sequentially start the remaining raw sewage pumps.
[3] 
Operation. Unit shall be capable of continuously running all raw sewage pumps, the minimum 6.5 KW accessory load, exterior lights and any other items requiring electricity to operate at the site.
[4] 
Unit shall be three-phase, 60 hertz and capable of delivering the required power as described above at 0.80 power factor.
[5] 
Frequency regulation shall not exceed 3 hertz from no load to rated load. Frequency variation shall not exceed plus or minus 0.3 hertz for constant loads from no load to rated load.
[6] 
Voltage regulation from no load to rated load shall be within plus or minus 2% of rated voltage for any size unit.
[7] 
Instantaneous voltage dip for all possible sequences of load application and motor starting for loads described in conditions of service shall not exceed 20% of nominal voltage.
[8] 
Sound attenuation: The unit shall be designed so that the maximum sound level generated shall not exceed 90 DB at a distance of 50 feet from the intake or the exhaust system. Sound readings shall be taken with generator operating under a full load condition. Applicant to provide certification from manufacturer.
(b) 
Engine generator control console mounted on the generating set.
(c) 
An automatic load transfer control to provide automatic starting and stopping of the plant and switching of the load.
(d) 
Mounted accessories and other equipment as specified.
(e) 
Weatherproof, heavy gauge painted steel or aluminum housing with removable side panels insulated as necessary.
(f) 
A rechargeable, minimum five-pound capacity fire extinguisher (Class ABC) mounted near the generator in a weatherproof enclosure.
(2) 
Control panels:
(a) 
Engine and generator control panels may be separate panels, or a combined panel, and mounted with vibration isolators on the unit in a NEMA 4 enclosure. Control module shall be located on the generator end of the set. Instruments shall be of direct-reading type, factory mounted and factory connected. Instruments shall be accurate within 3%.
(b) 
Provide engine panel with following minimum features and instruments:
[1] 
Three-position run-stop-remote switch.
[2] 
Manual starting switch.
[3] 
Full automatic starting from pilot device initiating start when normal power fails. Automatic cranking shall be interrupted cycle type not affected by ambient temperature with overall time limit. A total of three cranking cycles (approximately 10 seconds each) shall automatically shut down engine.
[4] 
Automatic engine shutdown for the following fault conditions:
[a] 
Overcrank.
[b] 
Overspeed.
[c] 
Low lube oil pressure.
[d] 
High engine temperature.
[5] 
Indicator lamps shall be provided to signal the following functions:
[a] 
Run. Indicates start disconnect.
[b] 
Overcrank. Indicates the starter has been locked out because cranking time was excessive.
[c] 
Overspeed. Indicates engine has shut down because of excessive rev/min.
[d] 
High engine temperature. Indicates engine has shut down because of critically high temperature.
[e] 
Low oil pressure. Indicates engine has shut down because of critically low oil pressure.
[f] 
Pre-high engine temperature. Indicates engine temperature is marginally high.
[g] 
Pre-low oil pressure. Indicates oil pressure is marginally low.
[h] 
Low engine temperature. Indicate engine temperature is marginally low for starting.
[i] 
Switch off (flashing). Indicates control switch is in the stop position.
[j] 
Low fuel. Indicated fuel supply is marginally low.
[k] 
Two spare faults (red), for future owner use.
[6] 
A fault reset switch shall be provided to clear fault indications and allow restarting of the engine after shutdown faults. The control design shall be such that the fault indication shall remain until reset. The fault indicator memory shall not be dependent on the presence of either AC or DC voltage and shall retain the fault status memory even through complete removal and replacement of the starting batteries. The fault reset function shall operate only when the run-stop remote switch is in the stop position.
[7] 
A locking screwdriver type potentiometer shall be provided to adjust the voltage ±5% from rated value.
[8] 
Manual reset exciter field circuit breaker.
[9] 
AC voltmeter, 90° scale, 2 1/2 inches (61.25mm) flange, 2% switchboard meter.
[10] 
AC ammeter, 90° scale, 2 1/2 inches (61.25mm) flange, 2% switchboard meter.
[11] 
Frequency meter 45-65 Hz., 90° scale, 1 1/2 inches (61.25mm) flange ±0.6 Hz panel meter.
[12] 
Four -position Ac meters phase selector switch to read line current and voltage in each phase with off position.
[13] 
Water temperature gauge.
[14] 
Ammeter charging circuit.
[15] 
Lubricating oil pressure gauge.
[16] 
Running time meter.
[17] 
Light with on/off switch for panel illumination.
(3) 
Appurtenances. All accessories needed for the proper operation of the pump station and generator shall be furnished. These shall include, but be limited to, the following:
(a) 
A painted critical-type exhaust muffler, and stainless steel flexible exhaust connection. Muffler shall be factory mounted on the housing with the condensate drain located at the bottom. To prevent birds from entering the muffler, a threaded exhaust piping extension shall be installed with the end of the piping cut at a 45 angle. The shortest end of the pipe shall be on the bottom.
(b) 
Aboveground fuel tank shall be the double-walled skid-type, mounted directly below the generator. Tank capacity shall be either 75 gallons or sufficient capacity to operate the generator at full load for 12 consecutive hours, whichever is greater. Aboveground storage tanks shall not exceed 660 gallons unless they conform to NFPA 30 and the Uniform Construction Code. Fuel system shall include fuel gauge, fuel lift pump (if recommended by generator manufacturer), and all necessary fuel piping. Fuel piping shall be Type K soft temper copper tubing, or as recommended, and installed by the manufacturer. All aboveground fuel storage tanks shall be designed and installed in conformance with NJDEP requirements.
(c) 
A mechanical governor capable of maintaining engine speed within 5% of synchronous speed from no load to full load shall be furnished.
(d) 
Control wires running between generator and transfer switch shall have termination identification on both ends. Identification shall be provided for each device or function and shall be silk-screened white on a black background.
(4) 
Paint:
(a) 
Unless otherwise noted, paint for exterior surfaces of equipment (including skids) shall be two coats of acceptable oil and heat-resistant paint, applied after surfaces have been thoroughly cleaned and prepared with suitable priming coat. Color for weatherproof housing and automatic transfer switch shall be green, unless otherwise approved.
(b) 
The generator muffler shall be protected with two coats of high heat aluminum paint. The paint system shall be primed in accordance with the manufacturer's recommendations.
(c) 
All painted surfaces damaged during installation shall be restored by the applicant/developer.
(5) 
Spare parts. Provide spare parts as recommended by manufacturer for six months of operation for each engine-generator set in addition to the following:
(a) 
One filter for each type of service.
(b) 
One fuse for each rating.
(6) 
Automatic load transfer control:
(a) 
The complete automatic load transfer control shall include the necessary relays and components parts, together with UL-listed and tested interlocked contactor, and shall provide the following functions:
[1] 
Upon normal power line outage, automatically start the pump station, and when the pump station comes up to voltage, disconnect the normal circuits from the main line and transfer them to the emergency pump station's output.
[2] 
Upon power line return, transfer the load back to the line and stop the pump station.
(b) 
Each contact pole of the main transfer device shall be double-break design, with solid silver cadmium contacts, capable of handling both noninductive and inductive loads and allow for inrush currents of 20 times the continuous rating. Contact pressure shall be maintained by a coil spring, not a part of the current-carrying path. The ampere rating of the transfer switch shall be sufficient to handle the capacity of the pump station and loads being transferred.
(c) 
The control shall contain either a twelve-volt or twenty-four-volt, fused, battery trickle charging circuit, with a rheostat and ammeter, to maintain starting batteries fully charged.
(d) 
The automatic transfer switch shall be provided with terminal lugs for copper wire and shall have individual, heat resistant chambers to protect against arcing. The transfer switch shall be provided with mechanical and electrical interlocks to prevent simultaneously energizing both normal and emergency service.
(e) 
The transfer switch shall be located in a NEMA 1 enclosure which is contained in a separate NEMA 4 enclosure, if skid mounted for outdoor use.
(f) 
Control accessories in the NEMA 1 enclosure shall mount on a dead front, swing out control accessory panel to avoid shock hazard while adjusting control functions, but will swing out exposing the wiring to facilitate servicing. Indicating lamps and meters shall be set in a front mounted panel to be visible with only opening the NEMA 4 enclosure door.
(g) 
Solid-state voltage sensors shall simultaneously monitor all phases of the normal source and all phases of the emergency source to provide adjustable range sensors for field adjustment for specific application needs. Voltage sensors shall be temperature compensated type, for maximum deviation over the temperature range of -20° F. to +175° F. Voltage sensors shall allow for adjustment to sense partial loss of voltage on any phase or normal or emergency source, even where motor feedback voltages exist.
(h) 
Controls shall signal the emergency power system to start upon signal from normal source voltage sensors. Solid-state time-delay start, adjustable from zero seconds to five seconds, shall avoid nuisance startups on momentary voltage dips or momentary interruptions.
(i) 
Switch shall transfer the load to the emergency power system after the generator set reaches proper voltage and frequency. Solid-state timer-delay transfer, adjustable from two seconds to 120 seconds, shall allow the engine-generator set to stabilize before application of load.
(j) 
The transfer switch shall control the generator set to allow generator set to start and transfer load within 10 seconds after normal source power failure.
(k) 
Switch shall retransfer the load to the normal source after normal power restoration. Solid-state time-delay retransfer, adjustable from zero minutes to 30 minutes, shall allow:
[1] 
Normal power to stabilize before retransfer.
[2] 
Staggered retransfer.
[3] 
Engine to run unloaded for cooldown before shutdown.
[4] 
Cooldown period shall be adjustable from zero minutes to 10 minutes.
(l) 
The operating power for transfer and retransfer shall be obtained from the source to which the load is being transferred. Controls shall provide an automatic retransfer of the load from emergency source to normal source if emergency source fails when normal source is available.
(m) 
Transfer switches shall have the "programmed transition" feature available by plugging the proper program timer into the factory installed timing receptacle. This provides the capability of either factory or field installation of this feature. This feature shall incorporate a field adjustable time delay of 1.5 seconds to 15 seconds. The time delay shall occur during switching in both directions, during which time the load is isolated from both normal and emergency sources. This will allow residual voltage components of motors or other inductive loads (such as transformers) to decay before completing the switching cycle. The program timer shall be connected in a manner that will not cause the time delay in switching, where the time delay as already been established by the loss of voltage to the load during normal source power interruptions. Transfer methods that use the phase relationships between the two power sources to control initiation time are not acceptable. Provide program timer.
(n) 
Status indicators.
[1] 
Controls shall provide built-in "control mode status indicators", consisting of LEDs to indicate a sequence of functions, such as the following:
[a] 
Source 1 OK.
[b] 
Two-wire run.
[c] 
Source 2 OK.
[d] 
Timing for transfer.
[e] 
Transfer command.
[f] 
Timing for retransfer.
[g] 
Retransfer command.
[h] 
Timing for stop.
[2] 
These indicators shall allow the operator to determine that the controls are properly sequencing and shall assist in determining sequence of any malfunctions that might occur.
(o) 
Provide position indicator lamps (green "NORMAL" and red "EMERGENCY") and a key operated selector switch to provide the following positions and functions:
[1] 
Test. Simulated normal power loss to control unit for testing of generator set, including transfer to load. Control system shall provide for "system test without load transfer" for use in that manner when desired.
[2] 
Normal. This is normal operating position and it restores the load to the normal source after test and after time delays.
[3] 
Retransfer. Momentary position to override retransfer time delay and cause immediate return to normal source after test or actual outage.
(p) 
Provide exerciser clock to set the day, time and duration of generator set period; also include "with/without load" selector switch. Clock shall have a one-week dial minimum. If normal power is interrupted while the generator is exercising at no load, the load is immediately transferred to the set.
(q) 
Provide battery charger, SCR voltage regulated type, with float and taper features; 12 or 24 VDC as required for generator set. Charger shall have charging ammeter and fuse protection. Charger shall not be damaged during engine cranking.
(r) 
Transfer switch capacity shall be no smaller than the disconnect switch capacity.
(s) 
Provide contacts to operate an alarm light in the dry well and a remote alarm indicating the generator is supplying power to the dry well. Upon automatic shutdown, the signal will be deactivated.
(7) 
Products:
(a) 
Single manufacturer. This equipment shall be manufactured by a single-source manufacturer who has been regularly engaged in the production of engine-generator sets. The emergency electric generating system described herein, including these components, shall be factory built, factory tested, and shipped by one source of supply and responsibility for warranty, parts and service. This manufacturer shall have a local representative who can provide factory-trained servicemen, required stock of replacement parts, and technical assistance.
(b) 
Safety standards. The electric generating system must meet all requirements of NFPA 110 (latest edition) including design specifications, prototype tests, one-step full-load pickup, and installation acceptance. Automatic transfer switch shall conform to UL 1008.
(c) 
The responsibility for performance to this specification includes the entire system and cannot be split up among individual suppliers of components comprising the system, but must be assumed solely by the supplier of the system.
(d) 
All controls shall be the standard of the manufacturer, who is engaged in the manufacture of engine-generator sets, transfer switches, and accessories and has then available for sale on the open market. Control parts shall be identified by part numbers of this manufacturer and shall have second source listing where applicable.
(8) 
Field quality control. Provide full load test utilizing portable test bank for four hours minimum. Simulate power failure including operator of transfer switch, automatic starting cycle, automatic shutdown and return to normal. All testing procedures shall be as described in NFPA 110 under Installation Acceptance.
(9) 
Personnel training. The generator manufacturer shall provide the services of a factory-trained representative for a minimum period of eight hours to perform initial startup of the generator, and to instruct the owner's personnel in the operation and maintenance of the equipment. Initial startup of generator shall conform to NFPA 110.
(10) 
Shop drawings and O&M manuals:
(a) 
Applicant's engineer to specify generator capacity and shall provide owner with backup information justifying the capacity selection. As a minimum, backup information shall identify motor horsepower and accessory load, motor voltage, motor code letter, starting sequence, and full or reduced voltage starting requirements. Manufacturer's load calculation sheets for both the specified generator and the furnished generator shall be submitted to the owner.
(b) 
Applicant shall provide eight copies of manufacturer's shop drawings for approval prior to fabrication. All eight copies will be utilized by the owner and the applicant shall furnish additional copies for his use. As a minimum shop drawings shall contain:
[1] 
Plan and elevation views with both overall and interconnection point dimensions, fuel consumption rate curves at various loads, ventilation and combustion air requirements, and electrical diagrams including schematic and interconnection diagrams.
[2] 
Product data showing dimensions, weights, ratings, interconnection points, and internal wiring diagrams for engine, generator, control panel, transfer switch, battery, battery rack, battery charger, exhaust silencer, vibration isolators and skid tank.
[3] 
Warranty data.
[4] 
Generator capacity with backup information justifying the capacity selection. As a minimum, backup information shall identify motor horsepower and accessory load, motor voltage, motor code letter, starting sequence, and full or reduced voltage starting requirements. Manufacturer's load calculation sheets for the furnished generator shall be submitted for approval.
(c) 
Provide 10 copies of the generator operations and maintenance manual, including, but not limited to:
[1] 
As-built plans of the concrete support pad and conduit locations.
[2] 
Suggested maintenance schedule and step-by-step maintenance procedures.
[3] 
Complete and detailed schematics of all electrical system and controls, including schematic and wiring diagrams for the engine alternator set, automatic transfer switch and an interconnecting diagram showing connections to individual components which constitute the standby power system.
[4] 
Complete and detailed exploded view drawings of all equipment. Include descriptions of all parts.
[5] 
Copy of all approved shop drawings.
(d) 
All operation and maintenance and warranty materials shall be submitted before testing of the generator takes place.
(11) 
Warranty. The complete standby electric power system, including engine-generator set and transfer switch equipped with set exerciser, and running time meter, shall be warranted for a period of five years or 1,500 operating hours, whichever occurs first, from the date of initial startup. During the warranty period, manufacturer shall promptly furnish the owner with replacement parts for all items deemed defective. Multiple warranties for individual components (engine, generator, controls, etc.) will not be acceptable. Satisfactory warranty documents must be provided. This warranty shall be detailed in available written documents. In the judgment of the owner, the manufacturer supplying the warranty for the complete system must have necessary financial strength and technical expertise with all components supplied to provide adequate warranty support.
J. 
Pump station site.
(1) 
Provide minimum seven-foot-high fence along the pump station area perimeter. All fence shall be located a minimum of 10 feet behind the present or future public right-of-way line or privately owned curbing and sidewalk. All slabs, equipment and utilities shall be located within the fenced area at least three feet from the fence.
(2) 
Adequate light and ventilation shall be provided at all pumping stations. Where operation or maintenance duties are required in enclosed areas or pits, forced ventilation by suitable means shall be provided with sufficient capacity to induce at least 30 air changes per hour. Explosion-proof equipment shall be utilized.
(3) 
Adequate fresh water facilities shall be provided to permit routine washdown and cleaning operations at all pumping stations. Where a domestic service connection is provided to a pumping station, the water supply shall be properly protected with an appropriate backflow prevention device. No cross-connections between fresh water and sewage pumps or pipes shall be permitted.
(4) 
Sewage pumping station structures and electrical and mechanical equipment shall be protected from physical damage by the 100-year flood. Sewage pumping stations shall remain fully operational and accessible during the twenty-five-year flood.
(5) 
The pumping station shall be readily accessible by maintenance vehicles during all weather conditions.
(6) 
A paved access road shall be provided for ingress and egress to the pump station. The access drive shall include a turnaround area.
(7) 
The entire site shall be fenced, and all appurtenances located within minimum 50 feet by 50 feet parcel.
(8) 
Site area lighting shall be provided and shall be shielded as necessary to protect adjacent uses from nuisance lighting.
(9) 
Sheared white pine screening, or approved substitution, shall be provided around the outside perimeter of the station fence. Provide an eight-foot-wide stone mulch area (six inches thick) with polyethylene wood barrier below starting out from the edge of the pump station pavement.
(10) 
Provide a source of potable water with a frostproof post hydrant and one inch hose bib connection.
(11) 
Within the pump station fenced-in area, provide a Woodford Iowa Model Y1 or approved equal freeze-proof post hydrant with one-inch inlet, three-quarter-inch threaded brass hose nozzle, three-quarter-inch galvanized steel pipe outer casing, one-eight-inch drain hole and furnished for four-foot depth of bury. Provide Nidel Model 34HD vacuum breaker-backflow preventer. Provide minimum one cubic yard of three-quarter-inch washed gravel below hydrant for drainage purposes.
(12) 
Provide 50 feet of three-quarter-inch heavy-duty, double layer nylon reinforced rubber water hose. Provide a high-pressure adjustable brass nozzle with adjustable spray pattern and removable barrel to fit the hose. Provide a galvanized steel hose rack on a stand located adjacent to the post hydrant. Stand shall be three feet high by two-inch diameter Schedule 40 stainless steel pipe with pipe cap. Set pipe two feet deep with twelve-inch diameter by two feet deep concrete footing. Bolt rack to pipe with 2-1/4-20 by three-inch stainless steel carriage bolts with self-locking nuts. Post hydrant, hose rack and stand shall all be painted green. Hydrant and stand to be located out of the motor vehicle traffic area. No connections between fresh water and sewage pumps or pipes shall be permitted.
(13) 
Pavement to extend six inches beyond fence perimeter. Apply tack coat conforming to NJDOT Standard Specifications Grade RC-70 or RC-T cutback asphalt or Grade SS-1 emulsified asphalt, Section 904.02 or 904.03, over entire stabilized base course.
(14) 
Extending from the wet well area pavement shall have minimum 0.75% slope towards fence. Finished surfaces shall be free from all roller marks, ridges and voids. Surfaces will not be acceptable if any puddling is possible or if slope is off more than 1/4 inch in 10 feet when tested in any direction.
(15) 
Provide a fifteen-foot-wide driveway up to the pump station gate. Cantilevered slide gate shall be minimum 12 feet wide. A motor vehicle entering the site shall have the ability to drive to both the wet well and dry well. The access drive shall include a turnaround area.
(16) 
All bolts, nuts, and washers whether buried, embedded in concrete or exposed above grade shall be stainless steel. All nuts and rods for harnessing shall be bituminous coated.
(17) 
The pump station property line shall extend to at least 10 feet outside the pump station fence and shall include the access road and turnaround area.
(18) 
Pump station shall include a bypass pumping valve pit. Valve pit shall be constructed per Township of Riverside standard detail.
(19) 
Sump pump piping sleeves and wet well joint leakage test. Before putting the pump station into operation, the contractor shall fill the wet well to the top with clean water to demonstrate both the sleeves connecting the wet well and dry well and all the wet well joints are watertight. Water level shall be maintained at top of the wet well slab for one hour by the contractor without the addition of water. Before the test commences, the contractor shall position a sufficient number of pumps to dewater the dry well in the event of a leak. If the test is unsuccessful, the contractor shall make repairs and retest sleeves as many times as is necessary.
(20) 
All tests shall be conducted in the presence of the Engineer.
(21) 
All pumping station sites must be provided with a street address on a separate parcel with a distinct lot and block number.
A. 
Description.
(1) 
Test gravity sanitary sewer for exfiltration and infiltration.
(2) 
Perform mandrel test on all gravity sanitary sewer lines.
B. 
Materials. Furnish pumps, valves, plugs, taps, pressure gauges, air compressor, and all other equipment required for testing of piping system.
C. 
Method of testing: exfiltration test for gravity sanitary sewer lines.
(1) 
General requirements:
(a) 
Perform all tests in presence of the Engineer.
(b) 
Conduct exfiltration test when all utilities (including gas, water, telephone, sewers), manholes, and laterals have been installed.
(c) 
Establish test sections between consecutive manholes as directed by the Engineer.
(d) 
All requirements of this specification shall be met prior to acceptance of sewer facilities by the Engineer.
(2) 
Procedure for exfiltration test (low pressure air test, 3.5 lbs.):
(a) 
Plug test section of sewer line at each end. Tap one plug and provide air inlet connection for filling pipe from air compressor.
(b) 
Cap or plug all service laterals, stubs and fittings connecting to sewer test section, brace same against internal pressure to prevent air leakage by slippage and blowouts.
(c) 
Connect air hose to tapped plug selected for air inlet. Connect other end of air hose to portable air control equipment used for controlling air entry rate to sewer test section and monitoring air pressure in pipeline.
(d) 
Air control equipment shall include shutoff valve, pressure regulating valve, pressure reduction valve and monitoring pressure gauge having pressure range from zero psi to five psi and an accuracy of +0.04 psi.
(e) 
Connect another air hose between air compressor (or other source of compressed air) and air control equipment. This completes test equipment set up.
(f) 
Supply air to test section slowly, filling pipeline until constant pressure of 3.5 psig is maintained. Air pressure must be regulated to prevent pressure inside the pipe from exceeding 5.0 psig.
(g) 
When constant pressure of 3.5 psig is reached, throttle air supply to maintain internal pressure above 3.0 psig for at least five minutes, permitting temperature of entering air to equalize with temperature of pipe wall. During this stabilization period, check all capped and plugged fittings with a soap solution to detect leakage at connections.
(h) 
If leakage is detected, release pressure in line and tighten all leaky caps and plugs. Start test operation again by supplying air. When necessary to bleed off air to tighten or repair faulty connection, a new five-minute interval shall be allowed after pipeline has been refilled.
(i) 
After stabilization period, adjust air pressure to 3.5 psig and shut off or disconnect air supply. Observe gauge until air pressure reaches 3.0 psig. At 3.0 psig commence timing with a stopwatch that is allowed to run until the line pressure drops to 2.5 psig. The time required, as shown on the stopwatch, for a pressure loss of 0.5 psig is used to compute air loss.
(j) 
If the time, in minutes and seconds, for the air pressure to drop from 3.0 to 2.5 psig is greater than that shown in Table 1 for designated pipe size, the section undergoing test shall have passed.
(k) 
If the time, in minutes and seconds, for 0.5 psig drop is less than shown in Table 1 for designated pipe size, the section of pipe shall have failed the test. Necessary repairs shall be made by the contractor and the line retested.
*Table 1
Time Requirements for Air Testing For Sewer Line of Uniform Pipe Size
Pipe Size
(inches)
Time
Minutes
Seconds
**4
2
32
**6
3
50
**8
5
6
10
6
22
12
7
39
14
8
56
15
9
35
16
10
12
18
11
34
20
12
45
21
13
30
NOTES:
*
Multi-pipe sizes: When sewer line undergoing test is eight-inch or larger diameter pipe and includes different sized laterals, the figure in Table 1 for uniform sewer main sizes will not give reliable or accurate criteria for the test. Where multi-pipe sizes are to undergo air testing, the Engineer will compute "average" size in inches which is multiplied by 38.2 seconds. The results give minimum time in seconds acceptable for pressure drop of 0.5 psig for "average" diameter pipe.
**
For eight-inch and smaller pipe only, if during the five-minute stabilization period pressure drops less than 0.5 psig after initial pressurization and air is not added, pipe section undergoing test shall have passed.
(3) 
Procedure for air pressure correction due to groundwater:
(a) 
Air pressure correction is required when prevailing groundwater is above sewer line being tested. Under this condition, air test pressure shall be increased 0.433 psi for each foot groundwater level is above invert of pipe.
(b) 
Establish height of groundwater (in feet) above pipe invert:
[1] 
During sewer and manhole construction, install one-half-inch diameter pipe nipple (threaded one or both ends, approximately 10 inches long) through manhole wall directly on top of one of sewer pipes entering manhole, with threaded end of nipple extending inside the manhole.
[2] 
Seal pipe nipple with a threaded one-half-inch cap.
[3] 
Immediately before air testing, determine groundwater level by removing the threaded cap from nipple, blowing air through the pipe nipple to remove any obstructions, and connecting clear plastic tube to pipe nipple.
[4] 
Hold plastic tube vertically permitting water to rise to groundwater level.
[5] 
After water level has stabilized in plastic tube, measure vertical height of water, in feet, above invert of sewer pipe.
(c) 
Determine air pressure correction, which is added to 3.0 psig normal starting pressure of test, by dividing the vertical height in feet by 2.31. The result gives air pressure correction in pounds per square inch to be added:
[1] 
Example: If the vertical height of water from the sewer invert to the top of the water column measures 11.55 feet, the additional air pressure required would be:
(11.55)
=
5 psig
2.31
[2] 
Starting pressure of the test would be 3.0 plus 5 or 8.0 psig, and the one-half-pound drop becomes 7.5 psig. There is not change in the allowable drop (0.5 psig) or in the time requirements established for the basic air test.
D. 
Methods of testing: infiltration test.
(1) 
General:
(a) 
All work relating to infiltration testing shall be performed in the presence of the Engineer.
(b) 
All requirements of this specification shall be met prior to acceptance of sewer facilities by the Engineer.
(2) 
Procedure for infiltration test:
(a) 
Examine the sanitary sewer system for infiltration at the downstream end of the system after construction has been completed.
(b) 
In the event that there is infiltration and water is flowing at the downstream end of the system, then the source and volume of flow shall be determined by an infiltration test.
(c) 
The test shall consist of isolating the source of infiltration by plugging the first upstream manhole and observing to see if the flow stops. This procedure is repeated one manhole at a time until each source has been isolated.
(d) 
When the infiltration has been isolated to a section or area, the volume of flow shall be determined using a 90° V-notch weir inserted into the pipe.
(e) 
The actual infiltration rate will be determined by the Engineer based on the weir measurements. This rate will be compared with the allowable infiltration rate of 50 gallons/inch diameter/mile of pipe/per day (24 hours).
(f) 
If the allowable infiltration rate is greater than the actual infiltration rate, the infiltration test passes. If the actual infiltration is greater than the allowable infiltration, the infiltration test fails.
(g) 
In the event the infiltration test fails, the section of the pipe involved shall be repaired as necessary and the test repeated.
E. 
Method of testing: mandrel.
(1) 
General:
(a) 
Mandrel test shall be performed on all gravity sanitary sewer lines.
(b) 
All work related to the mandrel test shall be performed in the presence of the Engineer.
(2) 
Procedure for mandrelling:
(a) 
Pipes shall be tested for deflection by passing a mandrel through the pipe without obstruction.
(b) 
The size of the mandrel shall be 92.5% of the base inside diameter of the pipe.
A. 
Description. Test sanitary sewer gravity and force mains for exfiltration.
B. 
Materials. Furnish pumps, valves, taps, pressure gauges, meter, and all other equipment required for testing of piping systems.
C. 
Method of testing: exfiltration test.
(1) 
General requirements:
(a) 
Perform all tests in presence of the Engineer.
(b) 
Conduct exfiltration test prior to backfilling trench.
(c) 
Establish test sections between valves, or as directed by the Engineer.
(d) 
All requirements of this specification shall be met prior to acceptance of force main by the Engineer.
(2) 
Procedure for exfiltration test:
(a) 
Expel air from pipe through blowoffs, or taps required for release of air from high points. Taps for release of air and blowoffs for filling pipe and releasing air shall be provided by the contractor.
(b) 
Fill each pipe section slowly with water, and subject pipe to hydrostatic pressure of 150 psi for one hour.
(c) 
When test pressure is reached, measure amount of make-up water required to maintain this pressure during the one-hour test period.
(d) 
Leakage shall not exceed 12 gallons per inch of diameter per mile of pipe per day. Pipelines failing to meet this requirement shall be repaired and retested as above specified.
(e) 
Compute leakage as follows:
[1] 
Gallons of make-up water x 24 = gallons loss/day.
[2] 
Gallons loss/day x feet of pipe testing = 5,280 feet/mile gallons/loss/mile/day.
[3] 
Gallons/loss/mile/day = Pipe dia. in inches.
Gallons loss/inch diameter/mile/day.
[4] 
Allowable exfiltration rate is 12 gallons/inch/diameter/mile/day.