[Adopted 10-7-1924]
Hereafter, when any street in the City of North Tonawanda shall have been ordered paved or repaved, such paving work shall not be commenced until all sewer pipes, gas pipes, water pipes or other pipes which shall be ordered laid or imbedded in said street where such pavement is to be made shall have been completed and the backfilling in the trenches made for such purposes shall have been completed and been so completed for a period of 90 days, and it shall be unlawful for any contractor or person doing such paving work to commence the construction of the same until such period has elapsed.