A. 
Description. The trench shall be excavated to full depth and grade for a distance of at least 50 feet in advance of pipelaying but not more than one average day's pipelaying in advance of the work. The trench shall be so braced and drained that the workers may work therein safely and efficiently. It is essential that the discharge from the trench dewatering pumps be conducted to natural drainage channels, drains or storm sewers.
B. 
Width of trench.
(1) 
The width of trench shall be ample to permit the pipe to be laid and jointed properly and the backfill to be placed and compacted as specified. Trenches shall be of such extra width, when required, as will permit the convenient placing of timber supports, sheeting and bracing and the handling of fittings.
(2) 
The minimum width shall be sufficient to give clearance of at least eight inches on either side of the barrel of the pipe.
C. 
Bell holes. Bell holes shall be provided at each joint to permit the jointing to be made properly.
D. 
Pipe clearance in rock. Ledge rock, boulders and large stones shall be removed to provide a clearance of at least six inches below and eight inches on each side of all pipes and fittings.
E. 
Excavation to grade.
(1) 
The trench shall be excavated to the depth required so as to provide a uniform and continuous bearing and support for the pipe on solid and undisturbed ground at every point between bell holes. Any part of the bottom of the trench excavated below the specified grade shall be corrected with approved material and thoroughly compacted as directed by the inspector. The finished grade shall be prepared accurately by means of hand tools.
(2) 
The subgrade beneath the center line of the pipe shall be finished to within 0.03 foot of a straight line between pipe joints or batter boards. All tolerance shall be above specified grade.
(3) 
If, in the opinion of the inspector, soil conditions are encountered at subgrade which require all or part of the work to be done in accordance with Subsection F, the inspector shall have the authority to order the work to be done.
F. 
Excavation in poor soil or rock.
(1) 
Where the bottom of the trench at subgrade is found to be unstable or to include ashes, cinders, all types of refuse, vegetable or other organic material, large pieces or fragments of inorganic material or rock which, in the judgment of the inspector, should be removed, the contractor shall excavate and remove such unsuitable material to the width and depth ordered by the inspector. Before the pipe is laid, the subgrade shall be made by backfilling with an approved material in three-inch uncompacted layers. The layers shall be thoroughly tamped, as directed by the inspector, so as to provide a continuous bearing and support for the pipe at every point between the bell holes. The finished subgrade shall be prepared accurately by means of hand tools.
(2) 
The subgrade beneath the center line of the pipe shall be finished to within 0.03 foot of a straight line between bell holes or batter boards, and all tolerances shall be above the specified grade.
G. 
Special foundation in poor soil. Where the bottom of the trench at subgrade is found to consist of material which is unstable to such a degree that, in the opinion of the inspector, it cannot be removed and replaced with an approved material thoroughly compacted in place to support the pipe properly, the contractor shall construct a foundation for the pipe, consisting of piling, timber or other materials, in accordance with plans approved by the Board of Public Works.
H. 
Blasting. Blasting for excavation will be permitted only after securing the approval of the inspector and only when proper precautions are taken for the protection of persons or property. The hours of blasting will be fixed by the inspector. Any damage caused by blasting shall be repaired by the contractor at his/her expense. The contractor's methods of procedure shall conform to state laws and municipal ordinances.
I. 
Braced and sheeted trenches.
(1) 
Open-cut trenches shall be sheeted and braced as required by any governing state laws and as may be necessary to protect life, property or the work. When close sheeting is required, it shall be so driven as to prevent adjacent soil from entering the trench either below or through such sheeting. Where sheeting and bracing are used, the trench width shall be increased accordingly.
(2) 
The inspector reserves the right to order the sheeting driven to the full depth of the trench or to such additional depths as may be required for the protection of the work. Where the soil in the lower limits of a trench has the necessary stability, the inspector, at his/her discretion, may permit the contractor to stop the driving of sheeting at some designated elevation above the trench bottom. The granting of permission by the inspector, however, shall not relieve the contractor in any degree from his/her full responsibility under the contract.
(3) 
Sheeting and bracing which have been ordered left in place must be removed for a distance of three feet below the established street grade or the existing surface of the street, whichever is lower. Trench bracing, except that which must be left in place, may be removed when the backfilling has reached the respective levels of such bracing. Sheeting, except that which has been left in place, may be removed after the backfilling has been completed or has been brought up to such an elevation as to permit its safe removal. Sheeting and bracing may be removed before flushing the trench, but only in such manner as will ensure the adequate protection of the completed water and/or sewer structures and prevent the disturbance of adjacent ground.
J. 
Care of surface material for reuse. All surface materials which, in the opinion of the inspector, are suitable for reuse in restoring the surface shall be kept separate from the general excavation material, as directed by the inspector.
K. 
Piling excavated material. All excavated material shall be piled in a manner that will not endanger the work and that will avoid obstructing sidewalks and driveways. Hydrants under pressure, valve pit covers, valve boxes, curb stop boxes, fire and police call boxes or other utility controls shall be left unobstructed and accessible until the work is completed. Gutters shall be kept clear or other satisfactory provisions made for street drainage, and natural watercourses shall not be obstructed.
L. 
Trenching by hand methods. Hand methods for excavations shall be employed in locations where obstructions are shown on drawings or where, in the opinion of the inspector, property can best be protected by digging by hand. In other locations, the contractor may use trench-digging machinery.
M. 
Barricades, guards and safety provisions. To protect persons from injury and to avoid property damage, adequate barricades, construction signs, torches, lanterns and guards, as required, shall be placed and maintained during the progress of the construction work and until it is safe for traffic to use the highway. All material piles, equipment and pipe which may serve as obstructions to traffic shall be enclosed by fences or barricades and shall be protected by proper lights when the visibility is poor. The rules and regulations of the local authorities respecting safety provisions shall be observed.
N. 
Maintenance of traffic and closing of streets.
(1) 
The contractor shall carry on the work in a manner which will cause the least interruption to traffic and may close to travel not more than two consecutive blocks, upon the specific permission of the city, including the cross street intersected. Where traffic must cross open trenches, the contractor shall provide suitable bridges at street intersections and driveways.
(2) 
The contractor shall post, where directed by the inspector, suitable signs indicating that a street is closed and necessary detour signs for the proper maintenance of traffic.
O. 
Structure protection. Temporary support, adequate protection and maintenance of all underground and surface structures, drains, sewers and other obstructions encountered in the progress of the work shall be furnished by the contractor at his/her expense and under the direction of the inspector. The structures which may have been disturbed shall be restored upon completion of the work.
P. 
Protection of property and surface structures. Trees, shrubbery, fences, poles and all other property and surface structures shall be protected unless their removal is shown on the drawings or authorized by the inspector. When it is necessary to cut roots and tree branches, such cutting shall be done under the supervision of the inspector.
A. 
Backfill material. All backfill material shall be free from cinders, ashes, refuse, vegetable or organic material, boulders, rocks or stones or other material which, in the opinion of the inspector, is unsuitable. However, from one foot above the top of the pipe to the subgrade of the pavement, material containing stones up to eight inches in their greatest dimension may be used, unless specified otherwise herein.
B. 
Use of excavated material as backfill. When the type of backfill material is not indicated on drawings or specifications, the contractor may backfill with the excavated material, provided that such material consists of loam, clay, sand, gravel or other material which, in the opinion of the inspector, is suitable for backfilling.
C. 
Sand or gravel backfill. Where sand or gravel backfill is not indicated on the drawings or specified herein and, in the opinion of the inspector, should be used in any part of the work, the contractor shall furnish and backfill with sand or gravel as directed.
D. 
Backfilling under pipe. All trenches shall be backfilled by hand, from the bottom of the trench to the center line of the pipe with sand, gravel or other approved material placed in three-inch layers and compacted by tamping. Backfilling material shall be deposited in the trench for its full width on each side of the pipe, fittings and appurtenances simultaneously.
E. 
Backfilling over pipe.
(1) 
From the center line of the pipe, fittings and appurtenances to a depth of one foot above the top of the pipe, the trench shall be backfilled by hand or by approved mechanical methods. The contractor shall use special care in placing this portion of the backfill so as to avoid injuring or moving the pipe.
(2) 
The backfill material from the center line of the pipe to one foot above the pipe shall consist of approved excavated material which shall be placed in three-inch layers and compacted by tamping.
F. 
Backfilling in freezing weather. Backfilling shall not be done in freezing weather except by permission of the inspector, and it shall not be made with frozen material. No fill shall be made where the material already in the trench is frozen.
G. 
Backfill sand. All sand used for backfill shall be a natural bank sand, graded from fine to coarse, not lumpy or frozen, and free from slag, cinders, ashes, rubbish or other material which, in the opinion of the inspector, is objectionable or deleterious. It shall not contain a total of more than 10% by weight of loam and clay, and all material must be capable of being passed through a three-fourths-inch sieve. Not more than 5% shall remain on a No. 4 sieve.
H. 
Backfill gravel. Gravel used for backfill shall consist of natural bank gravel having durable particles graded from fine to coarse in a reasonably uniform combination, with no boulders or stones larger than two inches in size. It shall be free from slag, cinders, ashes, refuse or other deleterious or objectionable materials. It shall not contain excessive amounts of loam and clay and shall not be lumpy or frozen. No more than 15% shall be finer than No. 200 sieve. Backfill gravel shall be used in the top 18 inches of backfill of all ditches in city streets.