Before recording of final subdivision plats or as a condition of final site plan approval or as a condition to the issuance of a zoning permit pursuant to N.J.S.A. 40:55D-65, the approving board may require and shall accept, in accordance with the standards adopted by this chapter, for the purpose of assuring the installation and maintenance of on-tract improvements:
A. 
The furnishing of a performance guaranty acceptable to the Borough's Chief Financial Officer in favor of the Borough in the amount of 120% of the cost of installation, which cost shall be determined by the Borough Engineer according to the method of calculation set forth in N.J.S.A. 40:55D-53.4, for improvements which the approving board may deem necessary or appropriate, including streets, grading, pavement, gutters, curbs, sidewalks, streetlighting, shade trees, surveyor's monuments as shown on the final map and required by the Map Filing Law, N.J.S.A. 46:23-9.9 et seq.,[1] water mains, culverts, storm sewers, sanitary sewers or other means of sewage disposal, drainage structures, erosion control and sedimentation control devices, public improvements of open space and, in the case of site plans only, other on-site improvements and landscaping. The Borough Engineer shall prepare an itemized cost estimate of the improvements covered by the performance guaranty, which itemized cost estimate shall be appended to each performance guaranty posted by the obligor.
[1]
Editor's Note: Said statute was repealed 2011, c. 217. See now N.J.S.A. 46:26B-1 et seq.
B. 
Provision for a maintenance guaranty, to be posted with the governing body for a period not to exceed two years after final acceptance of the improvement, in the amount of 15% of the cost of the improvement, which cost shall be determined by the Borough Engineer according to the method of calculation set forth in N.J.S.A. 40:55D-53.4. In the event that other governmental agencies or public utilities automatically will own the utilities to be installed or the improvements are covered by a performance or maintenance guaranty to another governmental agency, no performance or maintenance guaranty, as the case may be, shall be required by the municipality for such utilities or improvements.
A. 
The time allowed for installation of the improvements for which the performance guaranty has been provided may be extended by the governing body by resolution. As a condition or as part of any such extension, the amount of any performance guaranty shall be increased or reduced, as the case may be, to the amount of 120% of the cost of the installation, which cost shall be determined by the Borough Engineer according to the method of calculation set forth in N.J.S.A. 40:55D-53.4 as of the time of the passage of the resolution.
B. 
If the required improvements are not completed or corrected in accordance with the performance guaranty, the obligor and surety, if any, shall be liable thereon to the municipality for the reasonable cost of the improvements not completed or corrected and the municipality may, either prior to or after the receipt of the proceeds thereof; complete such improvements. Such completion or correction of improvements shall be subject to the public bidding requirements of the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.
A. 
Upon substantial completion of all required street improvements (except for the top course) and appurtenant utility improvements, and the connection of same to the public system, the obligor may request of the governing body in writing, by certified mail addressed in care of the Borough Clerk and the Borough Engineer, prepare, in accordance with the itemized cost estimate prepared by the Borough Engineer and appended to the performance guaranty pursuant to this article, a list of all incomplete or unsatisfactorily completed improvements. If such a request is made, the obligor shall send a copy of the request to the Borough Engineer. The request shall indicate which improvements have been completed and which improvements remain incomplete in the judgment of the obligor. Thereupon, the Borough Engineer shall inspect all improvements covered by the obligor's request and shall file a detailed list and report, in writing with the governing body, and shall simultaneously send a copy thereof to the obligor not later than 45 days after receipt of the obligor's request.
B. 
The list prepared by the Borough Engineer shall state, in detail, with respect to each improvement determined to be incomplete or unsatisfactory, the nature and extent of the incompleteness of each incomplete improvement or the nature and extent of, and remedy for, the unsatisfactory state of each completed improvement determined to be unsatisfactory. The report prepared by the Borough Engineer shall identify each improvement determined to be complete and satisfactory, together with a recommendation as to the amount of reduction to be made in the performance guaranty relating to the completed and satisfactory improvement, in accordance with the itemized cost estimate prepared by the Borough Engineer and appended to the performance guaranty pursuant to Subsection A of this article.
C. 
The governing body, by resolution, shall either approve the improvements determined to be complete and satisfactory by the Borough Engineer, or reject any or all of these improvements upon the establishment in the resolution of cause for rejection, and shall approve and authorize the amount of reduction to be made in the performance guaranty relating to the improvements accepted, in accordance with the itemized cost estimate prepared by the Borough Engineer and appended to the performance guaranty pursuant to this article. This resolution shall be adopted not later than 45 days after receipt of the list and report prepared by the Borough Engineer. Upon adoption of the resolution by the governing body, the obligor shall be released from all liability pursuant to its performance guaranty, with respect to those approved improvements, except for that portion adequately sufficient to secure completion or correction of the improvements not yet approved; provided that 30% of the amount of performance guaranty posted may be retained to ensure completion and acceptability of all improvements.
D. 
In the event that the obligor has made a cash deposit with the municipality or approving authority as part of the performance guaranty, then any partial reduction granted in the performance guaranty pursuant to this subsection shall be applied to the cash deposit in the same proportion as the original cash deposit bears to the full amount of the performance guaranty.
E. 
If any portion of the required improvements is rejected, the approving authority may require the obligor to complete or correct such improvements and, upon completion or correction, the same procedure of notification as set forth in this section shall be followed.
F. 
The obligor shall reimburse the municipality for all reasonable inspection fees paid to the Borough Engineer for the foregoing inspection of improvements, provided that the Borough may require of the developer a deposit for the inspection fees in an amount not to exceed, except for extraordinary circumstances, the greater of $1,000 or 10% of the cost of improvements, which cost shall be determined pursuant to N.J.S.A. 40:55D-53.4.