Upon final plan approval by the Authority, the applicant will be obligated
to the following procedures before initiating construction:
A. Preliminary approvals.
(1) Township approval. The applicant must furnish written
documentation of township approval of the project for construction.
(2) Preconstruction meeting. The applicant or his designated
construction manager must schedule a preconstruction meeting with the Authority's
representative to review all aspects of the proposed project and the construction
schedule. It is the contractor's responsibility to maintain a current
construction schedule and to notify the Authority of any changes to the schedule.
(3) List of contractors.
(a) A list of contractors, subcontractors and material suppliers
must be submitted for the Authority's approval. The list shall include
the name and telephone number of the person in charge of this contract for
each contractor and subcontractor.
(b) Where paving is involved, a point of contact and a phone
number shall be provided to ensure the immediate repair of temporary paving
deficiencies. A phone number for nonworking hours, evenings and holidays must
also be provided.
(4) Material samples. Material samples and material compliance
certifications shall be provided at the request of the Authority.
(5) Highway occupancy permit. The highway occupancy permit,
if applicable, will be obtained by the applicant in the name of Valley Forge
Sewer Authority. The applicant is responsible for the cost of the occupancy
permit (bonding, etc.) and the securing of any other municipal permits or
blasting bond.
(6) Start of construction. Construction shall not begin until
45 days after a letter of approval is issued by the Authority. It may begin
sooner with written permission by the Authority.
(7) Wetlands. If wetlands or other natural resources of concern
are involved, these areas shall be delineated in the field by a qualified
professional. The delineation shall be in such a manner that it is easily
recognizable during all phases of construction. It is the applicant's
responsibility to coordinate wetland delineation with the appropriate agencies.
(8) Preconstruction video. Where the construction is proposed
to traverse existing improved properties, a preconstruction video shall be
made to establish the original condition of the improved properties.
B. During construction.
(1) Inspection by the Authority.
(a) All construction must be conducted in accordance with
the latest edition of the Authority's technical specifications covering
sanitary sewage facilities. The Authority will designate a representative to act on the Authority's
behalf during construction. The cost for inspections performed by the representative
will be paid from the escrow established from the deposit of 15% of the cost
of the required sewerage improvements.
(b) The Authority's designated representative shall
make periodic visits to the site to observe the progress and quality of the
executed work and to determine, in general, if the work is continuing in accordance
with the Authority's specifications. He will not make exhaustive or continuous
on-site inspections to check the quality of the work. His efforts will be
directed toward providing assurance for the Authority that the completed sewage
facilities will conform to the requirements of the Authority's specifications.
(c) Neither the representative's authority to act under
this specification nor any decision made by him in good faith, either to exercise
or not to exercise such authority, shall give rise to any duty or responsibility
of the representative to the applicant, contractor, any subcontractor, any
of their agents or employees or any other persons performing any of the work.
(d) The representative will not be responsible for the construction
means, methods, techniques, sequences or procedures or the safety precautions
and programs incident thereto, and he will not be responsible for the applicant's
or contractor's failure to perform the work in accordance with the construction
documents and the Authority's specifications.
(e) The representative will not be responsible for the acts
or omissions of the applicant, contractor, any subcontractor, any of their
agents or employees or any other persons performing the work.
(2) Defective work. The Authority's representative shall
have the authority to disapprove or reject work which is defective, unsatisfactory,
faulty or does not conform to the requirements of the Authority's specifications.
Examples of defective work include, but are not limited to, separated pipe
joints, pipe misalignment at the manhole invert, inadequate slope and debris
in the pipelines.
(3) As-built drawings. The developer/applicant shall be responsible
for maintaining and submitting as-built drawings as prescribed in the General
Requirements, Section 01010, 1.07.
(4) Partial releases of financial security. As the work of
installing the required improvements proceeds, the party posting the financial
security may request the Authority to authorize the release of portions of
the financial security, as long as the progress of work remains satisfactory
to the Authority. The time frame for requests for progress releases will be
established at the preconstruction meeting and may not be less than 30 days.
Any such request shall be in writing to the Authority in accordance with the
following:
(a) At least 10 days prior to submitting the first application
for a progress release, the applicant shall submit a schedule of values for
the work, including quantities and unit prices aggregating the project estimate,
satisfactory in form and substance to the Authority, and subdividing the work
into component parts in sufficient detail to serve as a basis for progress
releases during construction. This schedule should include a category for
as-built drawings and for the Authority's Engineer to prepare the computer
model and mapping. Component parts should include cost per foot for pipe installations
and road restoration unit costs for manholes, etc.
(b) If the Authority approves the application, the Authority
will, within 45 days of presentation of a partial release estimate, authorize
a release to the applicant on the basis of the approved partial release estimate.
(c) The Authority will not authorize release of more than
90% of the amount due the applicant on account of the partial estimates. The
retainage will be held until the Authority issues a certificate of satisfactory
construction.
(d) A sample schedule of values is provided in Exhibit E as guidance for developing a schedule as well as for submitting
requests for progress releases.
C. Following construction.
(1) Inspection. Each lateral connection must be inspected
by the Authority's inspector before being backfilled. For connections
going online immediately, connection and tapping fees must be paid and a connection
permit obtained before connection is made. The connection will be inspected
to check fitting-to-main coinstallation, confirm no additional connections
have been made and examine materials used.
(2) Testing.
(a) Testing must be conducted in the presence of the Authority's
inspector and in accordance with the technical specifications. The costs for
the testing will be paid from the inspection escrow.
(b) Each section of pipe between manholes must be tested
in accordance with Section 02651 of the Technical Specifications before any lateral connections are made. No lateral connections
shall be made until all sections and manholes downstream of the lateral have
been deemed acceptable by the Authority's inspector.
(3) Guidelines for completeness.
(a) When the applicant considers the entire work ready for
its intended use, the applicant shall, in writing to the Authority's
inspector, certify that the work is substantially complete and request that
the inspector issue a certificate of satisfactory construction. Within 15
days thereafter, the applicant and the Authority's inspector shall make
an inspection of the work to determine the status of completion. If the inspector
does not consider the work substantially complete, he will notify the applicant,
in writing, giving his reasons therefor. If the inspector considers the work
substantially complete, he will prepare and deliver to the applicant a certificate
of satisfactory construction. There shall be attached to the certificate a
detailed list of each and every uncompleted item and a reasonable cost of
completion.
(b) Before the certificate of satisfactory construction is issued, the Authority requires the posting of financial security [See §
70-4D(7) for acceptable financial instruments.] to secure structural integrity of said improvements for a period of 18 months. The financial security shall be 15% of the actual cost of installation of the improvements.
Application for a permit shall be made by the owner of the improved
property to be served or by his duly authorized agent.
Building sewers shall in no case be less than four inches in diameter.
Where double or multiple homes are permitted to be served by a common building
sewer under a special connection permit issued by the Authority, the double
and multiple homes will be served with a six-inch line, unless a larger line
for the multiple homes is required by the Plumbing Inspector. An approved
adapter connecting the building sewer to the lateral must be used.
This Authority or its authorized representative (Plumbing Inspector)
shall have the right of access at reasonable times to any part of the improved
property served by the sewer system as shall be required for purposes of inspection,
measurement, sampling and testing and for performance of other functions relating
to service rendered by this Authority through the sewer system.
Upon connection to the sewer system, any septic tank and/or seepage
pit shall be abandoned, sanitized and filled with suitable material.