A minimum nonrefundable filing fee shall be paid for each plan
application submitted to the Board. Said fee shall be given to the
Planning Board upon submission of the plan. Checks shall be made out
to the Town of Great Barrington. See Appendix G for schedule of uses and average daily traffic (ADT).
For uses not found in Appendix G, ADT shall be as determined by the
current Trip Generation Manual of the Institute of Transportation
Engineers (ITE).
A. Fee for a Form A. The fee for a plan submitted for a Form A (subdivision
approval not required) shall be $125, regardless of the number of
lots shown.
B. Fee for a preliminary plan. The fee for a Form B (preliminary plan)
shall be $150, plus $50 per lot, or per average daily traffic (ADT)
increment of ten (10) based on the projected use, whichever is larger.
C. Fee for a definitive plan. The basic application fee for a Form C
(definitive plan) shall be $500, plus $100 per lot, or per average
daily traffic (ADT) increment of 10 based on the projected use, whichever
is larger.
Failure of the applicant to comply with the requirements of
the fee schedule in this article shall be deemed adequate cause for
disapproval of the plan.