[R.O. 2012 §525.090; Ord. No. A-5926 part 1 §A, 6-9-1994; Ord. No. A-7097, 10-26-2001]
A. Drainage Area Plan. A plan of the drainage area at a scale
of one (1) inch = one hundred (100) feet with two (2) foot contour
intervals using USGS Datum for areas less than one hundred (100) acres
or a plan of the drainage area at a scale of one (1) inch = three
hundred (300) feet with five (5) foot contour intervals for larger
areas. This plan shall include all proposed streets, drainage, and
grading improvements with flow quantities and direction of flow at
all critical points. All areas and sub-areas for drainage calculations
shall be clearly distinguished.
B. Hydraulic Data. Complete hydraulic data showing all calculations
shall be submitted. A copy of all nomographs and charts used in the
calculations shall be submitted if other than those included herein
are utilized.
C. Plan And Profile. A plan and profile of all proposed improvements
at a scale of 1 inch = 40 feet horizontal and 1 inch = 4 feet vertical
shall be submitted. This plan shall include the following:
1. Locations, sizes, flow line elevations and grades, type of pipe,
channels, boxes, manholes, and other structures drawn on standard
plan-profile sheets;
2. Existing and proposed ground line profiles along centerline of the
drainage improvement;
3. A list of the kind and quantity of material;
4. Typical sections and reinforcement of all boxes and channels;
5. Location of property lines, street paving, sanitary sewers, and other
utilities, both public and private.
D. Field Study. A field study of the downstream capacity of
all drainage facilities and the effect of additional flow from the
area to be improved shall be submitted. If the effect is to endanger
property or life, the problem must be solved before the plan will
be given approval.
E. Storm Water Flow Quantities. Storm water flow quantities
in the street shall be shown at all street intersections, all inlet
openings, and at locations where flow is removed from the streets.
This shall include the hydraulic calculations for all inlet openings
and street capacities. Street flow shall be limited according to Table
1 at the end of this Article.
F. Sinkholes Or Karst Areas. Sinkholes or karst areas shall
be clearly defined. If any portion of the storm water from an area
is to be drained into a sinkhole, all information available shall
be obtained and the capacity of the sinkhole shall be studied and
this study shall be submitted to determine the effect of the drainage
and pollution on ground water and streams.
G. Additional Information. Any additional information deemed
necessary by the Superintendent of Utilities for an adequate consideration
of the storm drainage effect on the City of Monett and surrounding
areas must be submitted.
H. Discharge
flow from the storm water detention outlet structure shall be directed
into existing channels, existing natural draws, watercourses, drainage
easements or to public rights-of-way. Discharge flow shall connect
to existing downstream storm sewers if directed by the City of Monett.
Discharge to Developed Property that Contains Existing
Structures or Improvements:
The developer shall obtain drainage easements across already-developed
property and construct facilities to drain to existing channels, existing
natural draws, watercourses, drainage easements, or to the public
right-of-way.
Discharge to Undeveloped Property that Does Not Contain
Existing Structures or Improvements:
The developer shall discharge water to a point, existing channel,
existing natural draw or water-course that will contain a drainage
easement in the future when the property develops.
[R.O. 2012 §525.100; Ord. No. A-5926 part 1 §B, 6-9-1994]
A. General Design Requirements.
1. All bridges shall be designed to accommodate a one hundred (100)
year frequency rain. Box culverts, pipe culverts, channels, and ditches
shall be designed to accommodate a one hundred (100) year frequency
rain at all locations having a drainage area in excess of 1.00 square
mile. Locations having a drainage area of less than or equal to 1.0
square mile shall be designed to accommodate a twenty-five (25) year
frequency rain.
2. Channel improvement types shall be as follows:
a. Improvements with a capacity of up to and including 10 C.F.S. shall
be open and (1) sodded; or (2) concrete paved invert; (3) concrete
lines; or (4) closed conduit;
b. Improvements with a capacity above 10 C.F.S. up to and including
100 C.F.S. shall be closed conduit;
c. Improvements with a capacity above the 100 C.F.S. up to and including
250 C.F.S. may be open and (1) concrete paved invert; or (2) concrete
lined; or (3) closed conduit;
d. Improvements with a capacity above 250 C.F.S. shall be open and (1)
concrete lined; or (2) have a 100 C.F.S. low flow paved invert.
B. Specific Requirements For Various Improvements.
1. Bridges and culverts. Bridges, box culverts, or
concrete pipe culverts shall be provided where continuous streets
or alleys cross watercourses. The structure shall be designed in accordance
with City specifications for materials and to carry HS-20 loadings
in all cases.
2. Closed storm sewers. Closed storm sewers shall either
be reinforced concrete box or pipe of approved type designed for HS-20
loadings. Reinforced concrete pipe or reinforced concrete boxes must
be used within two (2) feet of the back of the street curb and under
paved areas.
All storm sewers having trench walls within two (2) feet of
the back of the street curb shall be backfilled with granular material.
The use of corrugated steel, zinc-coated pipe and extra strength clay
pipe, will not be permitted within two (2) feet of the curb or under
pavement areas. All pipe materials shall meet the requirements of
the latest revision of the City of Monett Standard General Conditions
and Technical Specifications for Public Works Construction.
Grades for closed storm sewers shall be designed so that the
velocity shall not be less than three (3) feet per second nor exceed
twelve (12) feet per second. All other structures such as junction
boxes or inlets shall be in accordance with the Standard Drawings
adopted by the City of Monett.
Closed storm sewers shall extend to the furthest downstream
point of development with consideration given to velocities and to
providing discharge energy dissipators to prevent erosion and scouring
along downstream properties.
3. Open paved concrete channels. Grades for open paved
channels shall be designed so that the velocity shall not be less
than three (3) feet per second nor exceed twelve (12) feet per second.
Such concrete channels may be of different shapes according to existing
conditions; however, a channel with a flat bottom and 4:1 to 5:1 side
slopes is the most desirable type and shall be used whenever possible.
The thickness of channel paving shall depend on conditions at site
and size of channel; however, a minimum thickness of six (6) inches
is required. A six (6) inch freeboard must be provided. An eighteen
(18) inch toe wall is required at both the outlet and inlet ends of
the channel.
4. Open ditches (earth channels). Ditches shall have
a gradient that limits the velocity within 1.5 to 5.0 feet per second
depending on existing soil conditions. Such ditches shall have a minimum
side slope ratio of 3:1. The designer's attention is directed to the
fact that the Subdivision Regulations prohibit encroachment of buildings
and improvements on natural or designated drainage channels or the
channel's flood plains. Such flood plains are areas of land adjacent
to an open paved channel or an open sodded ditch that may receive
a flood condition from a one hundred (100) year frequency rain. The
limits of such flood plains shall be indicated on drainage improvement
plan.
[R.O. 2012 §525.110; Ord. No. A-5926 part 1 §C, 6-9-1994]
A. The
rate of runoff concentrated at any point shall be determined by the
Rational Formula:
|
Q
|
=
|
CIA, in which
|
|
Q
|
=
|
Runoff in cubic feet per second
|
|
C
|
=
|
The runoff coefficient for the area
|
|
I
|
=
|
Design rainfall intensity in inches per hour over the area based
on time of concentration and rainfall intensity curves included as
a part of this Article.
|
|
A 5-minute time of concentration is the minimum permitted.
|
|
A = Drainage area, in acres.
|
1. Runoff coefficient. The runoff coefficient "C" is
the variable in the Rational Formula least susceptible to precise
determination and the one that requires the greatest exercise of engineering
judgment because of the many area characteristics which affect the
coefficient. Among the factors to be considered in influencing the
runoff coefficients are the following: present and future zoning;
terrain; local ponding or depressions; the amount of pavement; roofs,
turf, and other areas having different degrees of imperviousness.
The selection of a coefficient should take into consideration
the probable ultimate development of presently undeveloped areas.
Suggested values of runoff coefficients are included in the following
table:
|
Suggested Runoff Coefficients "C"
|
---|
|
"C" Value
|
Surface Conditions
|
---|
|
.10-.15
|
Tall grass, brush
|
|
.15-.20
|
Parks, golf courses,farms, and one (1) acre single-family residences
|
|
.35
|
Single-family residences on lots of not less than 15,000 square
feet
|
|
.45
|
Single-family residences on lots of not less than 10,000 square
feet
|
|
.47
|
Single-family residences on lots of not less than 7,500 square
feet
|
|
.51
|
Single-family residences on lots of not less than 6,000 square
feet
|
|
.90
|
Gravel surfaces
|
|
.95
|
Asphalt and concrete surfaces
|
|
1.00
|
Buildings and other structures
|
2. Rainfall intensity. The average frequency of rainfall
occurrence used for design determines the degree of protection afforded
by a drainage system.
Maximum intensity of rainfall of a given expectancy is greater
for a short period of time than for longer periods. Therefore, it
is assumed that the maximum runoff will occur as soon as all parts
of the drainage area under consideration are contributing. The length
of time from the beginning of rainfall until runoff from the most
remote point in the drainage area reaches the point under consideration
is called the time of concentration. This may include overland flow
time and channel or gutter flow time. Nomographs which may be used
for determining time of concentration are reproduced at the end of
this Chapter. Once the time of concentration is known, the design
intensity rainfall may be determined from the rainfall intensity curves
developed from U.S. Weather Bureau data.
[R.O. 2012 §525.120; R.O. 2012 Tbl. 1 to Section 525.120; Ord. No. A-5926 part 1 §D, 6-9-1994; Ord. No. A-5926 Tbl. 1, 6-9-1994]
A. The
size of closed storm sewers, open channels, culverts, and bridges
shall be designed so that their capacity will not be less than the
runoff computed by using the Manning Formula:
Q = 1.486/n ar2/3 s1/2
Q = Capacity = Discharge in cubic feet/sec.
a = Cross sectional area of water in conduit or channel in square
feet
r = Hydraulic radius of water in conduit or channel = area/wetted
perimeter
s = Mean slope of hydraulic gradient in feet per foot
n = Roughness coefficient based on condition and type of material
of conduit or channel lining
B. Values
of "n" for various kinds of pipe for use in Manning Formula
|
Concrete Pipe
|
0.013
|
|
Corrugated Metal Pipe
|
0.024
|
|
Concrete Lined Channel
|
0.015
|
|
Earth Channels
|
0.030 to 0.050
|
C. Design Tabulations. For systems of storm sewers with inlets
in various locations, the time of concentration at any point will
be time of concentration at the most remote inlet upstream, plus the
flow time in the storm sewer to the point under consideration. Computations
for systems lend themselves readily to tabulation showing the drainage
area, time of concentration runoff, and capacity of each inlet and
section of sewer under consideration. This data is to accompany the
improvement plans.
|
TABLE 1 TO SECTION 525.120. STREET FLOW
|
---|
|
Street flow shall be limited by pavement encroachment and depth
of flow as follows:
|
|
Street Classification
|
*Maximum Encroachment of a two (2) year storm
|
|
Local
|
No curb overtopping. Flow may spread to crown of street
|
|
Collector
|
No curb overtopping. Flow spread must leave the equivalent of
one (1) ten (10) foot driving lane clear of water.
|
|
Arterials
|
No curb overtopping. Flow spread must leave the equivalent of
two (2) ten (10) foot driving lanes clear of water.
|
|
*Where no curbing exists, encroachment shall not extend past
property lines.
|
|
The storm sewer system shall commence at the point where the
volume of flow equals 5 cfs.
|