The Board of Trustees shall conduct a public hearing on the site plan within 62 days of the acceptance by the Board of Trustees of a completed application for site plan review, which shall be advertised in the Village's official newspaper at least five days before the public hearing. When required by General Municipal Law § 239-l and 239-m, the Board of Trustees shall submit notice of the public hearing, along with a complete description of the application, to the Tioga County Planning Board for review.
A. 
Within 62 days of the public hearing, the Board of Trustees shall render a decision. In its decision, the Board of Trustees may approve, approve with modifications, approve with conditions, or disapprove the site plan. The time period in which the Board of Trustees must render its decision can be extended by mutual consent of the applicant and the Board of Trustees.
(1) 
Approval. Upon approval of the site plan and payment by the applicant of all fees and reimbursable costs due the Village, the Board of Trustees shall endorse its approval on a copy of the site plan and shall immediately file it and a written statement of approval with the Village Clerk. A copy of the written statement of approval shall be mailed to the applicant by certified mail, return receipt requested.
(2) 
Approval with modifications or conditions. The Board of Trustees may conditionally approve the final site plan. A copy of a written statement containing the modifications required by the conditional approval will be mailed to the applicant by certified mail, return receipt requested. After adequate demonstration to the Board of Trustees that all conditions have been met, and payment by the applicant of all fees and reimbursable costs due the Village, the Board of Trustees shall endorse its approval on a copy of the site plan and shall immediately file it and a written statement of approval with the Village Clerk. A copy of the written statement of approval shall be mailed to the applicant by certified mail, return receipt requested.
(3) 
Disapproval. Upon disapproval of the site plan, the decision of the Board of Trustees shall immediately be filed with the Village Clerk and a copy thereof mailed to the applicant by certified mail, return receipt requested, along with the Board of Trustees' reasons for disapproval.
B. 
Expirations and extensions. A site plan approval shall expire one year after the date of final approval if actual construction has not been begun by the applicant. "Actual construction" is defined as the placing of construction materials in their permanent position fastened in a permanent manner, except that where a basement or cellar is being excavated, such excavation shall be deemed to be "actual construction."
(1) 
The Board of Trustees may, in its sole discretion, upon the applicant's written request made at least 30 days prior to the expiration of the initial one-year approval, grant an extension of time within which to implement the site plan, provided the applicant has made reasonable efforts to implement the site plan within the original one-year period, and further provided that no such extension shall exceed one year. No further extensions shall be permitted.
(2) 
An applicant whose site plan has expired may resubmit their application for a new site plan approval.