A. 
The municipality may include all costs incurred into the review fee charged to an applicant.
B. 
The review fee may include, but not be limited to, costs for the following:
(1) 
Administrative/clerical processing.
(2) 
Review of the SWM site plan.
(3) 
Review of an SWM site plan resubmission.
(4) 
Attendance at meetings.
(5) 
Inspections.
A. 
Fees may be established from time to time by the Borough in accordance with applicable laws to defray plan review and construction inspection costs incurred by the Borough. All fees shall be paid by the applicant at the time of submission of the SWM site plan.
B. 
Any fees established pursuant to this chapter may include, but not necessarily be limited to, any of the following:
(1) 
Administrative costs.
(2) 
Review of the SWM site plan by the Borough and the municipal engineer.
(3) 
Site inspections.
(4) 
Inspection of stormwater management facilities and stormwater management improvements during construction.
(5) 
Final inspections.
(6) 
Any additional work required to enforce provisions of this chapter, correct violations, and assure proper completion of stipulated remedial actions.
C. 
Should the Borough's actual costs exceed the fees submitted by the applicant, the Borough may invoice the applicant for the difference. Such payment will be submitted by the applicant to the Borough within 30 days of invoice receipt.