[Amended 3-13-1978 by Ord. No. 0-78-5; 9-10-1990 by Ord. No.
0-90-20]
A. The applicant shall submit to the Secretary of the
Planning Board four copies of the final site plan and four copies
of the application.
B. Upon determination of completeness of the application
by the Director of Planning and Zoning or his designee, 15 copies
of the final site plan and application shall be submitted by the applicant
to the Secretary of the Planning Board for distribution to the Development
Review Committee.
[Amended 12-12-2007 by Ord. No. 0-07-25]
C. The Development Review Committee shall review the
final site plan and determine whether or not the application includes
all the information required for review. Should the application be
determined either to be incomplete or require substantial revisions,
the applicant shall be notified within 45 days of submission and may
thereafter submit an appropriately revised application to the Secretary
of the Planning Board as in the first instance.
D. After review by the Development Review Committee and
at least 10 days prior to the meeting at which action on the final
site plan is desired, the applicant shall mail copies of the minor
site plan and application to the individual members of the Planning
Board. The applicant shall submit two copies of the final site plan
and application to the Secretary of the Planning Board.