[R.O. 2012 §510.080; CC 1979 §27-32]
All grading and excavating necessary in the construction of sidewalks, curbing or guttering, unless the grading of that portion of the roadway has been done previously, may be included in the same contract with the sidewalks, curbing or guttering, as required by law, and the cost thereof, if included in the contract, may be included in the special tax bills issued for the payment of the improvement.
[R.O. 2012 §510.090; CC 1979 §27-33]
The contractor shall, before the work of constructing sidewalks, curbing or guttering is accepted, remove therefrom all rocks, broken stone, litter or trash of any kind and leave the street and work in good condition and ready for use.
[R.O. 2012 §510.100; CC 1979 §27-34]
All curbs, gutters and private driveways shall be constructed on the true grade, curb and cross section lines of the streets along and upon which they may be ordered and shall be done under the supervision of the Superintendent of the Department of Streets and Public Improvements.
[R.O. 2012 §510.110; CC 1979 §27-35]
No sidewalk, curb, gutter or other improvement mentioned in this Article, which does not meet the specifications herein prescribed, shall be accepted; provided, that on sidewalk, curb or gutter construction, where opposite curbs differ in elevation or vary from the true grade or where improvements already built do not conform to the established grade, or where necessary for drainage, the Superintendent of the Department of Streets and Public Improvements may order or allow a variation from the established grade, not to exceed six (6) inches.