Easements shall be established for all on-site stormwater management
or drainage facilities, including but not limited to detention facilitates
(above or below ground), infiltration facilities, all stormwater BMPs,
drainage swales, and drainage facilities (inlets, manholes, pipes,
etc.).
Easements shall provide ingress to and egress from a public right-of-way.
In lieu of providing an easement to the public right-of-way, a note
may be added to the plan granting the City of Harrisburg or its designees
access to all easements via the nearest public right-of-way.
The following note shall be placed on the recorded plan: "Nothing
shall be planted or placed within the easement which would adversely
affect the function of the easement or conflict with any conditions
associated with such easement."
A note shall be placed on the SWM site plan identifying the party
responsible for assuring the continued functionality and required
maintenance of any easement.