[Added 10-3-2016 by Ord. No. 16-40C]
A. 
Any person, firm, corporation or other legal entity engaged in a new construction project or substantial improvement project must provide suitable toilet facilities, maintained in a sanitary condition, for use by workers during construction.
B. 
Each construction project must provide at least one toilet facility with the following exception: if two separate projects on two adjacent properties are being constructed by the same general contractor, then only one toilet facility will be required for both projects.
C. 
In the event of a predicted natural disaster or major flooding condition, all portable toilet facilities must be removed or anchored at the construction site no later than 24 hours prior to the forecasted storm occurrence time.