Property owners installing renewable energy systems shall be
required to provide the interconnection application between the renewable
energy developer and the electric distribution company (National Grid)
and any documentation of program enrollment (e. g., renewable energy
growth or net metering enrollment forms) to the Town indicating if
the renewable energy system is net-metered or if the system is selling
a portion or all of the energy produced back to National Grid under
the Renewable Energy Growth Program. A copy of the final interconnection
service agreement executed between the renewable energy developer
and electric distribution company shall be provided to the Town prior
to construction of the renewable energy system.