[Amended 9-21-1992 by L.L. No. 8-1992; 9-21-1998 by L.L. No.
7-1998]
A. Permit required. Any one or combination of the following
shall require a building/use permit:
(1) Any building, structure, installation, use or occupancy required to obtain a permit under Chapter
110, Housing Standards, of the Village Municipal Code.
(2) The construction, erection or placement of any building
or structure.
(3) The expansion, addition or alteration of a building
or structure that would in any way alter its exterior dimensions,
its interior structural members or the provision for entrance or exit.
(4) The introduction of any new, additional, changed or
expanded use; except the use of a one- or two-family dwelling unit
previously used for that same, respective purpose.
(5) The alteration of any shoreline or major landform.
B. Application. There shall be submitted with all applications
for a building/use permit a minimum of three copies, and such additional
copies as the Code Enforcement Official may specify, of a layout or
plot plan drawn to scale in ink on a minimum sheet size of 8 1/2
inches by 11 inches showing the actual dimensions of the lot to be
built upon, the exact size and location on the lot of any existing
and proposed principal and accessory buildings and such other information
as may be necessary to determine and provide for the administration
and enforcement of these regulations in accord with the following:
(1) Where the Code Enforcement Official determines that
the application involves a project whose estimated cost or size requires
the preparation and certification of plans in accordance with the
provisions of the New York State Education Law, Articles 145 and 147,
such application and all supporting plans and documentation shall
be prepared by a licensed professional engineer or registered architect
as is appropriate.
(2) Any application for a certificate of compliance shall
be made coincidental with any application for a building/use permit,
such application to be valid for the duration of the building/use
permit. Application for a certificate of compliance shall be made
by the property owner or by his or her agent duly authorized, in writing,
to act on the property owner's behalf.
C. Notification of determination. The date the application
is received by the Code Enforcement Official shall be the effective
date of submission for all time parameters established under these
regulations, provided that such application is found to be complete
and sufficient, which determination shall be made within seven days
of the date of receipt by the Code Enforcement Official. The Code
Enforcement Official shall issue or refuse to issue the applied for
building/use permit or advise the applicant of any required additional
information or referral required within seven days of receipt of the
application. Notice of refusal to issue any permit shall be given
to the applicant, in writing, and shall state the reasons for said
refusal. Approval of the application shall be indicated by issuance
of the building/use permit.
D. Duration of validity. A building/use permit issued
under these regulations shall expire and thereafter be deemed null
and void unless actual construction, erection or placement of the
applied-for use has been conclusively initiated within 90 days from
the date the permit is issued, except as an extension of this time
period is applied for and, for due cause shown, granted by the Code
Enforcement Official. Such permit shall continue in force and effect
for a maximum duration of 12 months unless an extension of this time
period is applied for and, for due cause shown, granted by the Code
Enforcement Official.
[Amended 9-21-1998 by L.L. No. 7-1998]
A. Certificate required. No building or use requiring
a building/use permit shall be used or occupied and no use otherwise
required by these regulations to obtain an initial or subsequent certificate
of compliance shall continue beyond the time frame provided unless
a certificate of compliance shall have been issued by the Code Enforcement
Official.
B. Application. Application for a certificate of compliance
shall be made coincidental with any application for a building/use
permit or as otherwise specifically stated. Such application shall
be valid for the duration of the validity of the building/use permit
or as otherwise specifically stated.
C. Notification of determination. The Code Enforcement
Official shall make or cause to have made an inspection of each building
or lot for which a certificate of compliance is required before issuing
such certificate. Such inspection shall be made within seven days
from the date of notification of project completion. A certificate
of compliance shall be issued only if the proposed use of the building
or land conforms to the applicable provisions of these regulations
and to that plot plan, purpose and description for which the building/use
permit was issued. Issuance of this certificate or written notification
of refusal to issue the same and the reasons therefor are to be accomplished
within 15 days from the date of notification of project completion.
[Amended 9-21-1998 by L.L. No. 7-1998]
A. Certificate required. The owner or his duly designated
representative of any existing business sign or existing mobile home
park shall make application for and obtain a certificate of registration.
B. Application. Application for a certificate of registration shall be made for the required uses within six months from the effective date of these regulations. The application shall consist of that information required under §
180-32, Site plan review, and the review of said application by the Planning Board shall be in accord with the provisions of the site plan review process.
C. Notification of determination. The Planning Board
shall, within six months from the date of application, authorize issuance
of a certificate of registration.
D. Duration of validity and renewal. The certificate
of registration shall be valid for a period of two years from its
date of issuance. Six months prior to its expiration date, an application
will be filed for its renewal for a subsequent period of two years.
E. Compliance. No addition or change to the use as identified
in the certificate shall be made unless and until a revised application
is made and approved in accord with the process identified herein.
Failure to apply for an initial certificate of registration within
six months from the effective date of these regulations or failure
to comply in every regard with the conditions and stipulations of
a certificate of registration once issued shall constitute a violation
of these regulations.
[Amended 9-21-1992 by L.L. No. 8-1992; 9-21-1998 by L.L. No.
7-1998]
A. The Board of Trustees may, on its own motion, on petition
or on the recommendation of the Planning Board or Board of Appeals,
after public notice and hearing, amend the requirements and district
boundaries established by these regulations.
B. All proposed amendments originating by petition or
by motion of the Board of Trustees shall be referred to the Planning
Board for a report and recommendation thereon. The Planning Board
shall submit its report on or before the date of any scheduled public
hearings.
C. Before any amendment to these regulations, including
the Zoning Map, there shall be public notice and a hearing thereon
as provided by law.
D. After the public hearing and referral to and a report
by the Planning Board, a majority vote of the members of the Board
of Trustees shall be required to amend the regulations, except in
the issuance of a protest petition.
E. If a protest petition against a proposed amendment
is presented to the Board of Trustees, duly signed and acknowledged
by the legitimate parties in interest as provided for under § 7-708
of the Village Law, such amendment shall not become effective except
by the favorable vote of at least 3/4 of the members of the Board
of Trustees.
F. A super majority vote of the Board of Trustees is
necessary for changes to the requirements and district boundaries
established by these regulations in the face of a challenge by the
owners of 20% of the area of land that is affected by the change.
[Amended 11-16-1992 by L.L. No. 10-1992; 9-21-1998 by L.L. No. 7-1998]
A. A public hearing shall be required prior to action
on any amendment, interpretation, special use or variance considered
under these regulations.
B. The Board of Trustees shall hold any public hearing
in consideration of an amendment to these regulations in accordance
with the applicable requirements of law.
C. The Board of Appeals shall hold any public hearing
in consideration of a request for interpretation or variance in accordance
with the applicable requirements of law.
D. The Planning Board shall hold any public hearing in
consideration of a request for a special use permit in accordance
with the applicable requirements of law.
E. Public notice of any required public hearing will
be advertised in a newspaper of general circulation in the village
at least five days prior to the date of such hearing and shall specify
the date, time, place and purpose of such hearing.
F. The hearing shall be conducted in accord with the
guidelines established by the presiding officer. Any person or party
of interest may appear in person, or by agent or attorney, and shall
be given an opportunity to be heard as it is relevant to the proceeding.
[Amended 9-21-1998 by L.L. No. 7-1998]
A. Whenever any special use, site plan, variance or amendment
would change the district classification of, or a proposed regulation
apply to, real property within 500 feet of the following:
(1) The boundary of the village or town; or
(2) The boundary of any existing or proposed county or
state park or any other recreation area; or
(3) The right-of-way of any existing or proposed county
or state road or highway; or
(4) The existing or proposed boundary of any county-owned
or state-owned land on which a public building or institution is situated;
or
(5) The boundary of a farm operation located in an agricultural
district, as defined by Article 25AA of the Agriculture and Markets
Law, except that this subsection shall not apply to the granting of
area variances, said proposed special use, site plan, variance or
amendment shall be referred to the St. Lawrence County Planning Board
which shall have 30 days in which to report its recommendations to
the village body from which it was referred. Failure of the County
Planning Board to report within 30 days, or such longer period as
may have been agreed upon by it and the referring agency, the municipal
body having jurisdiction to act may do so without such report.
B. Notification of action taken on any matter previously
referred to the County Planning Board will be given to the County
Planning Board within seven days of the date of such action.
[Amended 9-21-1998 by L.L. No. 7-1998]
A. Enforcement. These regulations shall be enforced by
a person designated by the Board of Trustees and herein referred to
as the "Code Enforcement Official," who shall in no case grant any
permit, certificate of compliance or certificate of registration for
any building or use where such would be in violation of any provision
of the regulations. The Code Enforcement Official shall make such
inspections as are necessary to carry out his duties.
B. Citizen complaint. Any resident, property owner or
other person of legitimate interest may file with the Code Enforcement
Official a written, signed complaint against any alleged violation
of these regulations.
C. Investigation, notification and correction procedure.
The procedure involving enforcement of these regulations shall be
as follows:
(1) The Code Enforcement Official shall investigate the complaint and, depending on his determination, may issue a correction notice to the responsible party as appropriate. The Code Enforcement Official may, at any time upon his discovery of a violation of these regulations, issue a correction notice without a complaint, as noted in §
180-41B.
(2) A record shall be made by the Code Enforcement Official
of any building or use which is in violation of these regulations,
which shall include, in addition to the violations, appropriate information
containing the date, time and manner in which notice was given and
to whom. Notice may be given in person or by certified mail, return
receipt requested.
(3) The responsible party shall correct such noted violations
within 30 days from the date of notification. If any such alleged
violation is not corrected or corrective action is not commenced within
that period, the Village Administrator may, upon application made
by the responsible party within such thirty-day period, grant one
thirty-day extension where deemed feasible.
(4) Any failure to comply with said notice shall be reported,
in writing, by the Code Enforcement Official to the Village Administrator
within 10 days of the last date for compliance as given in the notice.
Failure to comply with this report within the ten-day period shall
not preclude any further regular procedures the village may subsequently
undertake.
(5) Upon the receipt of such report, the Village Administrator
shall bring the matter to the attention of the Village Board which
shall, at a regular or special Village Board meeting, take action
to direct the Village Attorney to institute proceedings to compel
compliance and to correct violations as are hereinafter provided for.
(6) The Code Enforcement Official may, where he deems
it necessary in the instance of a building under construction or the
location of any new or altered use, issue a stop-work order to preclude
the continued and further violation of these regulations. Such stop-work
order shall stay all activity in conjunction with any violation of
these regulations. Any such stop-work order will stipulate that within
30 days a permit or certificate will be obtained noting compliance
with these regulations. If said permit or certificate is not obtained
by the responsible party or if the work continues in violation of
the stop-work order, action by the village will be initiated to compel
compliance, by injunction, and to assess such penalties as are hereinafter
provided for.
D. Violations and penalties shall be as follows:
(1) Any person or corporation, whether as owner, lessee,
agent or employee, who or which shall violate any of the provisions
of these regulations or who or which fails to comply with any order
or requirement made thereunder or who or which erects, alters, moves,
initiates or continues use of any building or land in violation of
any requirement or application under the provision of these regulations
shall be guilty of a violation and, upon conviction, shall be punished
by a fine not exceeding $250 or imprisonment not exceeding 15 days,
or both, in accordance with the applicable provisions of law.
(2) Each week (seven days) that the violation continues
shall constitute a separate and additional instance of violation.
(3) In case any building, structure or land is erected,
constructed, reconstructed, altered, converted or maintained or any
building, structure or land is used in violation of these regulations,
the Board of Trustees, in addition to other remedies, may institute
any appropriate action or proceedings to prevent such unlawful erection,
construction, reconstruction, alteration, conversion, maintenance
or use; to restrain, correct or abate such violation; to prevent the
occupancy of said building, structure or land; or to prevent any illegal
act, conduct, business or use in or about such buildings, structure
or land.
E. Appeal. All appeals for relief from the application of these regulations in matters of interpretation or requests for variances shall be directed to the Board of Appeals, which Board shall function as prescribed previously in §
180-34 of these regulations. Where the Board finds that practical difficulty or unnecessary hardship may result from strict compliance with these regulations, it may vary the requirements of these regulations so that substantial justice may be done and the public interest secured, provided that such variations will not have the effect of nullifying the intent and purpose of these regulations or the Village General Development Plan (1984-1985), and as such plan may be subsequently amended. In granting such variances, the Board of Appeals shall require such conditions as will, in its judgment, secure substantially the objectives of the standards or requirements so varied.
F. Article 78 Proceeding.
(1) Application to Supreme Court by aggrieved persons.
Any person or persons, jointly or severally aggrieved by any decision
of the Board of Appeals or any officer, department, board or bureau
of the village may apply to the Supreme Court for review by proceeding
under Article 78 of the Civil Practice Law and Rules. Such proceeding
shall be instituted within 30 days after the filing of a decision
of the Board in the Office of the Village Clerk.
(2) Costs of appeal. Costs shall not be allowed against
the Board of Appeals, unless it shall appear to the Court that it
acted with gross negligence or in bad faith or with malice in making
the decision appealed from.
(3) Preference of appeal to Court. All issues in any proceeding
under this section shall have preference over all other civil actions
and proceedings.
(4) Power of Court. If, upon the hearing at the Supreme
Court, it shall appear to the Court that testimony is necessary for
the proper disposition of the matter, it may take evidence or appoint
a referee to take such evidence as it may direct and report the same
to the Court with his or her findings of fact and conclusions of law,
which shall constitute a part of the proceedings upon which the determination
of the Court shall be made. The Court may reverse or affirm, wholly
or partly, or may modify the decision brought up for review determining
all questions which may be presented for determination.
[Amended 9-21-1998 by L.L. No. 7-1998]
A. Interpretation. In their interpretation and application,
the provisions of these regulations shall be held to be minimum requirements,
adopted for the promotion of the public health, safety or the general
welfare. Whenever the requirements of these regulations are at variance
with the requirement of any other lawfully adopted rules, regulations
or ordinances, the most restrictive, or that imposing the higher standard,
shall govern.
B. Severability. The invalidity of any provisions of
these regulations shall not invalidate any other provision thereof.
C. Invalidity. No approval, permit or certificate authorized
or granted by any official of the village in contradiction to the
provisions of these regulations shall vest any right or interest to
the recipient irrespective of any action taken or obligation incurred
in reliance on such authorization, nor shall the village be liable
for the same under any such invalid authorization.
D. Liability. Nothing in these regulations, including
the issuance of a building/use permit, certificate of compliance or
certificate of registration, shall be construed to ensure or in any
way guarantee any building, structure, improvement, installation or
use against defect, failure or other shortcoming; and the village
shall not be liable for the same.
E. Fees. A schedule of fees for the administration of
these regulations in consideration of an application for any building/use
permit, certificate of compliance, certificate of registration, variance
or amendment shall be as established by resolution of the Board of
Trustees.
F. Effectuation. The Village Board of Trustees of the
Village of Potsdam, County of St. Lawrence, New York, does hereby
ordain and enact the Village of Potsdam Zoning Regulations under and
pursuant to the Municipal Home Rule Law of the State of New York and
in accord with Village Law, § 7-700, of Chapter 892 of the
Laws of 1972. The Village of Potsdam Zoning Regulations, as herein
amended, shall become effective upon adoption by the Board of Trustees
at the time and in the manner provided by law; and any existing local
ordinances, statutes, resolutions, regulations or laws in conflict
with its provisions shall be deemed repealed upon their effective
date.
G. Continuation. Nothing herein shall be deemed to exempt
or release any prior or current building, structure, improvement,
installation or use from any requirements, stipulations or pending
actions under any village requirements in force and effect prior to
the effective date of these regulations. In particular, no use established
or maintained in violation of the previous Village Zoning Ordinance shall be released from any liability thereunder, and the
continuation of such violation shall similarly be considered a violation
of these regulations.