The Building Inspector or his deputies (hereinafter, Inspector) shall conduct all plumbing and drainage system and plumbing system inspections required herein and shall issue such permits as may be required.
There shall be the following inspections by the Inspector of work done pursuant to plans and specifications approved as hereinafter provided:
A. 
The first inspection shall be made when all the lines of soil, sewer connection, waste and vent pipes, with all their respective branches, are in place and before any work has been covered or concealed. At this inspection, the work shall be tested by the water test in the presence of the Inspector. Any joint appearing at this inspection to be defective must be made tight, and any defective pipe then discovered must be replaced by sound pipe.
B. 
An inspection for leaks shall be made when the work is completed.
C. 
In case the Inspector, at first inspection or at any time thereafter, prior to the issuance of a certificate by the Inspector hereinafter provided, shall deliver to the plumber in charge of the work a written statement of any particular or particulars in which the work violates any provision or provisions of this chapter, there shall be such inspections in addition to those hereinabove provided as shall be necessary for the Inspector to find out whether the violation has been cured; provided, however, that such inspection shall, if possible, be a part of the inspection specified in Subsections A and B above.
The plumber shall give to the Inspector prompt notification whenever the work is ready for any of the inspections herein provided. The Inspector shall make inspections within a reasonable time after receiving such notification.
A. 
If the Inspector finds that the work conforms to this chapter, he shall give to the plumber a certificate to that effect.
B. 
No plumbing and drainage system and plumbing system shall be used until after the certificate hereinabove provided for has been given.
When the Inspector condemns all or part of any plumbing or drainage system or plumbing system installation, the owner may, within five days after receiving written notice from the Inspector, file a petition, in writing, with the Village Clerk for review of said action of the Inspector. Upon receipt of this petition, said request shall be referred to a duly authorized and qualified person from the State of New York Codes Division to review the request to determine if said plumbing installation complies with the New York State Uniform Code and shall make a decision in accordance with its findings.
A. 
Application. Before any plumbing, drainage system or plumbing system work is started in the Village or before any additions or alterations are made to old work, an application on regular printed forms, properly filled out in ink and signed by a licensed master plumber, shall be filed in the office of the Inspector, together with plans and description, in duplicate, showing and describing the proposed work and repairs to existing plumbing, drainage system or plumbing system. No plumbing, drainage system or plumbing system work shall proceed until the appropriate plans and specifications referred to in this section have been approved, in writing, by the Inspector.
B. 
Modifications. Modifications of original approved plans shall not be permitted, unless such changes are approved by the Inspector, on written request, made by the owner, architect or licensed master plumber.
C. 
Permit fees. Plumbing permit fees, payable to the Village of Mamaroneck, are as set forth in Chapter A347, Fees.