The purpose of the preliminary plan is to achieve formal approval
of the preliminary plan in order to minimize the need for revisions
when final plans are submitted.
Submission deadline. The applicant shall submit a proper application for a preliminary plan. Such plan shall be submitted and reviewed in accordance with § 175-28 of this chapter.
Requirements. The preliminary plan submitted shall provide the information required by § 175-26 and should conform to any changes recommended during the sketch plan procedure if a sketch plan was submitted.
Revised/resubmitted plans. Revisions to submitted plans shall be
coordinated with the Township Engineer's comment letter. Revisions
shall be "bubbled" and "highlighted" and denoted with the comment
letter's itemized comment number.
Plans required. The following plans shall be required for all major subdivisions and land developments and shall show the information set forth in Subsections B through K as applicable. Plans may be combined if, in the discretion of the Planning Commission, clarity of the plan will not be impaired.
Plans shall be prepared, signed and sealed by a professional engineer,
professional land surveyor or landscape architect (operating within
their jurisdiction pursuant to the requirements of their licensing
boards) on a standard sheet of 24 inches by 36 inches or 30 inches
by 42 inches, except when the Planning Commission approves of other
size plans. Standard sheet size shall be consistent throughout the
entire plan set of the application.
Each sheet shall be numbered and shall show its relationship to the
total number of sheets. If match lines are employed, a legend showing
sheet relationship shall be provided.
Where any revision is made or when the plan is a revision of a previously
approved plan, dotted lines shall be used to show features or locations
to be abandoned and solid lines to show the currently proposed features.
Notations of revisions shall be dated.
Name, address, signature and seal to the professional's statement
(See Appendix A.[1]) of any licensed engineer, surveyor or landscape architect
(functioning pursuant to the restrictions as set forth by their licensing
boards) responsible for the preparation of the plan.
In nonresidential developments and planned residential developments,
the arrangement and use of buildings and parking areas, with all necessary
dimensions and number of parking spaces. Elevations and perspective
sketches of proposed buildings are encouraged.
Rights-of-way, restrictive covenants and easements for all drainage,
utilities or other purposes. Easements shall be defined by bearings
and distances.
Sight distances shall be shown at the intersection of any proposed
street with existing streets. Sight distances shall be measured pursuant
to PennDOT requirements.
If the developer is not an individual, then the developer's
principal officers and any person or entity holding an ownership interest
of 10% or more in the entity.
Location map shall show roads and parcels and zoning district
lines. The required scale of the map is not to be specified. The map
shall encompass an area of eight inches by eight inches centered around
the site. USAS maps shall not be used.
The plans shall contain a certification from the developer's professional engineer that any revised - resubmitted plans contain only those changes brought to the attention of the Township as prescribed in § 175-25C and § 175-28C.
Map of entire contiguous holdings and all other holdings of
the owner within 1,000 feet, indicating area of proposed subdivision.
A sketch plan of proposed road systems will be required for area not
included in the preliminary plan.
Existing and proposed contour lines at intervals of two feet if the
slope is 15% or less, five feet if the slope is over 15% and up to
20% and 20 feet if the slope exceeds 20% shall be shown. Contour intervals
shall be based on a field survey or photogrammetric procedure.
If any detention or retention structures are used, the plans
shall include a detailed plan view and profile views drawn at least
to a horizontal scale of one inch equals 50 feet.
Existing and proposed contour lines at intervals of two feet
if the slope is 15% or less, five feet if the slope is over 15% and
up to 20% and 20 feet if the slope exceeds 20% shall be shown. Contour
intervals shall be based on a field survey or photogrammetric procedure.
Map of all property holdings of the owner within 2,000 feet of the
proposed subdivision, indicating the site of proposed subdivision.
A sketch plan of a proposed road system with any property holdings
contiguous to the proposed subdivision.
Public. When the subdivision is to be served with water by an
existing water company or authority, the developer shall submit two
copies of a letter from the water company or authority which states
that the company or authority can adequately serve the subdivision
and which states any conditions required by the company or authority
for the provision of services.
The approval of the subdivision shall be conditioned upon the
receipt by the Township of the approval of the system by the appropriate
agencies prior to final plan submission.
The Planning Commission and Supervisors shall have the right
to review any such preliminary and final plans to determine the overall
adequacy of the proposed system in accordance with Appendix C[5] and/or DEP regulations.
The developer shall submit two copies of a letter from the company
or authority which states that the company or authority can adequately
serve the subdivision and which states any conditions required by
the company or authority for the provision of services.
The Planning Commission and Supervisors shall have the right
to review any such preliminary and final plans to determine compliance
and compatibility of the same with any Township plans or studies and
the overall adequacy of the proposed system.
The approval of the subdivision shall be conditioned upon the
receipt by the Township of the approval of the sewerage and treatment
system by the appropriate state and federal agencies.
The approval of the subdivision shall be conditioned upon the
receipt by the Township of the approval of the land planning modules
by the appropriate state and federal agencies.
The Planning Commission and Supervisors shall have the right
to review any such preliminary and final plans to determine compliance
and compatibility of the same with any Township plans or studies and
the overall adequacy of the proposed system in accordance with Appendix
B[6] and/or DEP regulations.
The approval of the subdivision shall be conditioned upon the
receipt by the Township of the approval of the land planning module
by the appropriate agencies.
A statement setting forth, in detail, the character of the improvements
the applicant proposes to make on the property to be developed and
a development schedule indicating the approximate date when construction
can be expected to begin and be completed.
In areas where there are problems concerning groundwater availability
or quality, the Planning Commission or the Board of Supervisors shall
require the developer to submit for review a hydrogeological report.
Said report shall be prepared by a qualified and certified professional
engineer, geologist or hydrologist who is approved by the Township,
and shall contain the following information:
Determine capacities of major production wells
and general groundwater use in area of the proposed subdivision, including
identification of overpumped areas and critical recharge areas, if
any.
Determine availability of groundwater and dewatering
effects, including impacts of impervious surfaces and stormwater management
facilities on groundwater recharge capacity.
Developers of subdivisions or land developments generating in
excess of 100 round trips per day shall be required by the Planning
Commission or the Board of Supervisors to submit for review a traffic
impact study. The study shall indicate increases projected in vehicular
traffic and the ability of the existing road system to accommodate
traffic increases and should be prepared in accordance with standards
set forth by the American Association of State Highway and Transportation
Officials, Pennsylvania Department of Transportation and any other
recognized institute of authority.
Storm drainage calculations. All calculations relating to facilities appearing on the grading and storm drainage plan and the erosion and sedimentation plan shall be submitted for review by the Township Engineer. See Chapter 163, Stormwater Management.
Other utilities. The applicant shall submit letters of commitment
from the proposed utilities (i.e., water, sewer, electric, telephone,
CATV, gas, etc.)
Sinkhole occurrences. Whenever a subdivision or land development
or part thereof is in an area of carbonate geology as mapped in the
attachment,[7] the following provisions shall apply.
A recognized professional with competence in the field shall
review aerial photographs, soils and other related data available
to him or her, as the data relates to the subject property. The professional
shall also conduct a site inspection of the property.
Based on the work required in Subsection L(10)(a), the professional shall prepare a map of the site showing all karst features or feature indicators. The mapping shall indicate, but shall not be limited to, the following features:
Based upon the work performed in Subsection L(10)(a), the professional shall determine what further testing should be done by the applicant to ensure compliance with the performance standards set forth in § 175-42Q. Testing methodology shall be reasonable under the circumstances, including:
The applicant shall cause the additional testing established in Subsection L(10)(c) to be done. The test results shall be included with the submission and shall be referred to the Municipal Engineer.
The Township Engineer shall report to the Planning Commission,
with a copy to the landowner, his or her opinion as to the adequacy
of the study and as to the capability of the site to support the proposed
development in a manner in which the risks attendant to development
in carbonate areas are either eliminated or minimized. Recommendations
for site development, including stormwater management, the layout
of utility lines and building location may be included. Additional
studies or testing as deemed necessary by the Township Engineer in
order to produce an adequate study, given the scale of the proposed
development and the hazards revealed, may be required of the applicant.