A. 
Prior to and during construction, all the soil erosion and sediment control measures shall be subject to inspection and approval by the Municipal Engineer, who shall be notified by the developer at least 24 hours prior to the start of construction. No underground installation shall be covered until inspected and approved.
B. 
When all of the necessary and appropriate soil erosion and sediment control measures have been completed, the developer shall notify the Mayor and Township Council in writing, by certified or registered mail, of the completion of the aforesaid soil erosion and sediment control measures and shall send a copy thereof to the Municipal Engineer. The Municipal Engineer shall inspect all of the aforesaid soil erosion and sediment control measures. The Municipal Engineer shall thereupon file a report, in writing, with the Mayor and Township Council. Said report shall be detailed and shall indicate either approval, partial approval or rejection. If said soil erosion and sediment control measures, or any portion thereof, shall not be approved or shall be rejected by the Municipal Engineer, said report shall contain a statement of reasons for such nonapproval or rejection. Where said report indicates partial approval of said soil erosion and sediment control measures, it shall indicate the cost of the soil erosion and sediment control measures for which approval is rejected or withheld. Where partial approval is granted, the developer may be released from all liability pursuant to its performance guaranty bond, except for that portion adequately sufficient to secure the soil erosion and sediment control measures not yet approved. No approval for occupancy of any building will be granted unless all needed soil erosion control measures have been completed or substantially provided for in accordance with this chapter. The developer shall bear the final responsibility for the installation and construction of all required soil erosion and sediment control measures according to the provisions of this chapter.
C. 
The municipality may issue a stop construction order if a project is not being executed in accordance with a certified plan.
[Added 5-15-1978 by Ord. No. 78-9]
D. 
A certificate of occupancy shall be withheld unless there has been compliance with the provisions of a certified plan for permanent measures to control soil erosion and sedimentation.
[Added 5-15-1978 by Ord. No. 78-9]
E. 
A formal report of compliance must be filed with the municipal agent authorized to issue certificates of occupancy. A copy of this report shall be sent to the Sussex County Soil Conservation District.
[Added 5-15-1978 by Ord. No. 78-9]