A development permit shall be obtained before construction or development begins, including placement of manufactured homes, within any area of special flood hazard established in Section
38-7. Application for a development permit shall be made on forms furnished by the Engineer and may include, but not be limited to: plans in duplicate, drawn to scale, showing the nature, location, dimensions and elevations of the area in question; existing or proposed structures, fill, storage of materials, drainage facilities; and the location of the foregoing. Specifically, the following information is required:
A. Elevation, in relation to mean sea level, of the lowest floor (including
basement) of all structures.
B. Elevation, in relation to mean sea level, to which any structure
has been floodproofed.
C. Certification by a registered professional engineer or architect that the floodproofing methods for any nonresidential structure meet the floodproofing criteria in Section
38-17; and
D. Description of the extent to which any watercourse will be altered
or relocated as a result of proposed development.
The Township Engineer is hereby appointed to administer and
implement this chapter by granting or denying development permit applications
in accordance with its provisions.
Duties of the Township Engineer shall include, but not be limited
to:
A. Permit review.
(1) Review all development permits to determine that the permit requirements
of this chapter have been satisfied.
(2) Review all development permits to determine that all necessary permits
have been obtained from those federal, state or local governmental
agencies from which prior approval is required.
(3) Review all development permits to determine if the proposed development is located in the floodway, assure that the encroachment provisions of Section
38-18 are met.
B. Use of other base flood and floodway data. When base flood elevation and floodway data has not been provided in accordance with Section
38-7, Basis for establishing the areas of special flood hazard, the Engineer shall obtain, review, and reasonably utilize any base flood elevation and floodway data available from a federal, state or other source, in order to administer Sections
38-17A, Specific standards, Residential construction, and 38-17B, Specific standards, Nonresidential construction.
C. Information to be obtained and maintained.
(1) Obtain and record the actual elevation (in relation to mean sea level)
of the lowest floor (including basement) of all new or substantially
improved structures and whether or not the structure contains a basement.
(2) For all new or substantially improved floodproofed structures:
(a)
Verify and record the actual elevation (in relation to mean
sea level); and
(b)
Maintain the floodproofing certifications required in Section
38-12C.
(3) Maintain for public inspection all records pertaining to the provisions
of this chapter.
D. Alteration of watercourses.
(1) Notify adjacent communities and the New Jersey Department of Environmental
Protection, Dam Safety and Flood Control Section and the Land Use
Regulation Program prior to any alteration or relocation of a watercourse,
and submit evidence of such notification to the Federal Insurance
Administration.
(2) Require that maintenance is provided within the altered or relocated
portion of said watercourse so that the flood-carrying capacity is
not diminished.
E. Interpretation of FIRM boundaries. Make interpretations, where needed, as to the exact location of the boundaries of the areas of special flood hazard (for example, where there appears to be a conflict between a mapped boundary and actual field conditions). The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in Section
38-15.