A. 
The subdivider or site plan applicant shall provide for the ultimate installation of the following on-site and off-site improvements:
(1) 
New public street and roadway: when such items of construction are not covered by the "Standards," the NJDOT Standards of Highway and Bridge Construction shall apply.
[Amended 5-13-1997by Ord. No. 97-8]
(2) 
Approved street signs.
(3) 
Curbs and gutters.
(4) 
Sidewalks, when required by the Planning Board.
[Amended 5-13-1997by Ord. No. 97-8]
(5) 
No topsoil shall be removed from the site or used as spoil except in accordance with the provisions of Chapter 248, Soil Movement, of the Code of the Borough of Hillsdale. All replaced or redistributed topsoil shall be stabilized by seeding, planting or such other method as may be specified in the soil moving permit to ensure that it will remain in place and free from erosion.
(6) 
Monuments. Monuments shall be of the size and shape required by N.J.S.A. 46:23-9.11 and shall be placed in accordance with said statute.
(7) 
Utilities (including sewage disposal systems, storm drains and culverts, water and gas mains and electrical supply lines for light, power and telephone service), hydrants and connections thereof with approved existing and proposed systems.
(8) 
Streetlighting.
[Amended 5-13-1997by Ord. No. 97-8]
(9) 
Shade trees. Shade trees shall be located on the street line so as not to interfere with utilities or sidewalks and shall be one of the following types: Shade Maple, Sycamore or an equivalent approved by the Planning Board.
B. 
The subdivider or site plan applicant shall, at its own cost, provide for the ultimate installation of all off-tract water, sewers, drainage and street improvements and easements therefor required by the Planning Board in connection with the subdivision or site plan if such off-tract improvements:
(1) 
Are wholly made necessary by the subdivision or site plan or the improvement therein; and
(2) 
Do not confer material benefits on any land other than the land within the subdivision or site plan.
C. 
The subdivider or site plan applicant shall provide for payment of its proportionate share, allocated in accordance with this Part 5, of the cost of the ultimate installation of all off-tract water, sewer, drainage and street improvements and easements therefor required by the Planning Board in connection with the subdivision or site plan if such off-tract improvements:
(1) 
Are wholly or partially made necessary by the subdivision or site plan or the improvements thereon; and
(2) 
Confer benefit on lands other than those within the subdivision or site plan.
D. 
In addition to the improvements set forth in Subsections A, B and C of this section, the site plan applicant shall, upon the conditions delineated by the Planning Board, provide for the ultimate installation, prior to issuance of a certificate of occupancy, of the following:
(1) 
Buffer landscaping and foundation plantings.
(2) 
On-site paved parking areas and all appurtenant curbs, islands, lighting and driveways.
(3) 
Fencing and screening.
(4) 
On-site lighting.
(5) 
On-site pedestrian ways.
E. 
All such improvements shall meet the design standards of this chapter.
All of the improvements installed by a subdivider or site plan applicant shall be subject to inspection and approval by the Borough Engineer, who shall be notified by the subdivider or site plan applicant at least 24 hours prior to the start of construction. No underground installation shall be covered until so inspected and approved.