A. 
The Township Engineer or their assignee shall inspect phases of the installation of the permanent stormwater management facilities as deemed appropriate by the Township Engineer. It is the responsibility of the permittee to notify the Township Engineer 48 hours in advance of the beginning of construction of stormwater management facilities. Individual residential on-lot stormwater management systems shall be inspected by Township staff.
B. 
During any stage of the work, if the Township Engineer determines that the permanent stormwater management facilities are not being installed in accordance with the approved stormwater management plan, the Township shall revoke any existing approvals issued under this chapter until a revised drainage plan is submitted and approved, as specified in this chapter.
C. 
All work is required to be completed in accordance with the Lower Windsor Township Construction and Materials Specification for Land Development, originally dated October 9, 2003, including most recent update.