In all areas of special flood hazards, the following standards of this Article
V are required.
In all areas of special flood hazards where base flood elevation data has been provided as set forth in §§
159-6, Basis for establishing the areas of special flood hazard, and 159-17, Use of other base flood and floodway data, the following standards are required:
New construction or substantial improvements of structures including manufactured homes shall have the lowest floor, including basement, elevated to or above the base flood elevation as may be determined in §
159-17 or two feet above the highest adjacent grade where no elevation data is available.
A. New construction or substantial improvements of structures including
manufactured homes shall have the lowest floor (including basement)
elevated at least two feet above the highest adjacent grade next to
the proposed foundation of the structure.
B. Fully enclosed areas below the lowest floor that are subject to flooding
shall be designed to automatically (without human intervention) allow
for the entry and exit of floodwaters for the purpose of equalizing
hydrostatic flood forces on exterior walls. Designs for meeting this
requirement must either be certified by a licensed professional engineer
or a licensed architect or meet the following criteria:
(1) A minimum of two openings having a total net area of not less than
one square inch for every square foot of enclosed area subject to
flooding;
(2) The bottom of all such openings shall be no higher than one foot
above the lowest adjacent finished grade;
(3) Openings may be equipped with louvers, valves, screens or other coverings
or openings provided they permit the automatic entry and exit of floodwaters.
Located within areas of special flood hazard are areas designated as floodways (see §
159-4, Definitions). The floodway is an extremely hazardous area due to high velocity floodwaters carrying debris and posing additional threats from potential erosion forces. When floodway data is available for a particular site as provided by §§
159-6 and
159-17, all encroachments, including fill, new construction, substantial improvements, and other development, are prohibited within the limits of the floodway unless a technical evaluation demonstrates that such encroachments shall not result in any increase in flood levels during the occurrence of the base flood discharge.