This Article XXXIV of the Land Use Ordinance shall be known and may be cited as the "Bridgewater Township Hillside Development Ordinance."
It is the purpose of this Article XXXIV to protect the health, safety and welfare of people and property within the Township of Bridgewater from improper construction, building and development on steep slope and hillside areas in the Township of Bridgewater, and more particularly, but without limitation, to reduce the peculiar hazards which exist in hillside areas by reason of erosion, siltation, flooding, soil slippage, surface water runoff, pollution of potable water supplies from nonpoint sources, destruction of unique and predominant views, and it is a further purpose of this Article XXXIV to encourage appropriate planning, design and development sites within hillside areas which preserve and maximize the best use of the natural terrain and maintain ridgelines and skylines intact.
A. 
This Article XXXIV shall apply to all applications for development in the Township of Bridgewater.
B. 
The Planning Board shall approve all plans submitted under this Article XXXIV as part of any application for site plan approval or subdivision approval.
C. 
The Township Engineer, after referral to and recommendation by the Environmental Commission in appropriate cases, shall approve all applications for building permits for compliance with this Article XXXIV if not previously approved under Subsection B above.
A. 
Applicants for site plan approval, subdivision approval or a building permit shall submit to the Planning Board Clerk or Engineering Department, as the case may be, all information and documents (exhibits) required by this Article XXXIV.
B. 
The Planning Board Clerk shall process all exhibits submitted under this Article XXXIV in the same manner as applications for subdivision approval or site plan approval.
C. 
The Engineering Department shall refer applications for building permits, where compliance with this Article XXXIV has not been previously granted, to the Environmental Commission for review and recommendation. The application shall be accompanied by all exhibits required in this Article XXXIV.
D. 
If the application for a building permit involves land where development is proposed only on slopes of 10% or less, the Township Engineer or his designee may waive referral to the Environmental Commission and approve the application as being in compliance with this Article XXXIV.
A. 
For all sketch plats, sketch site plans and applications for building permits, the following exhibits shall be submitted:
(1) 
Topography map showing existing contours at two-foot intervals.
(2) 
Areas clearly identified showing the following slopes as measured between ten-foot contour lines per § 126-266:
(a) 
Area 1: 30% or higher.
(b) 
Area 2: 20% to 29%.
(c) 
Area 3: 11% to 19%.
(d) 
Area 4: 0% to 10%.
(3) 
Calculations, in square footage and acres, of amount of area in the various slope categories listed above.
B. 
Only where development is proposed on slopes greater than 10%, as part of preliminary subdivision approval, preliminary site plan approval and for applications for building permits, the following additional exhibits, prepared by a qualified individual or firm, as determined by the Planning Board with the advice of the Environmental Commission, may be required to be submitted:
(1) 
Extent and erodibility potential of exposed soils.
(2) 
Length, steepness and surface roughness of exposed slopes.
(3) 
Resistance of soil to compaction and stability of soil aggregates.
(4) 
High-water table, water infiltration capacity and capacity of soil profile.
(5) 
Chemical, physical and biological nature of subsurface soils.
(6) 
Type and location of construction activity, including the amount of site grading.
(7) 
The time period of exposure of erodible soils during construction.
(8) 
The area and density of woodlands and forests, referenced to the vegetation map of the Township's natural resources inventory, within the construction site and on contiguous lands for a distance of 500 feet. All significant tree specimens eight inches in diameter, within the work area shall be indicated on the development plans as well as physically marked on the construction site.
[Amended 11-18-1991 by Ord. No. 91-33]
(9) 
The extent of impervious surface to be constructed.
(10) 
Location of construction access roads.
(11) 
Calculation of amount of site grading, to include a cut-and-fill balance sheet, including cross sections, and indicating, where applicable, the volume of and source of off-site fill.
A. 
The Planning Board or Township Engineer, as the case may be, shall review and approve only those applications where development plans and necessary improvements accomplish the following:
(1) 
Control velocity and rate of water runoff so that such velocity and rate are no greater after construction and development than before and all other provisions of the Bridgewater Township Stormwater Control and Floodplain Ordinance have been complied with.
(2) 
Minimize stream turbidity and changes in flow.
(3) 
Protect environmentally vulnerable areas.
(4) 
Stabilize exposed soils both during and after construction and development.
(5) 
Prevent soil slippage.
(6) 
Minimize number and extent of cuts to prevent groundwater discharge areas.
(7) 
Preserve maximum number of trees and other vegetation on the site and avoid the critical upland forest areas as shown on the vegetation map of the Township's natural resources inventory.
B. 
The Planning Board or the Township Engineer, as the case may be, may impose such conditions upon any approval as said Board or Engineer deems necessary to achieve the above stated goals. All permanent improvements necessary to achieve the above criteria shall be bonded in the same manner as set forth in the Subdivision Ordinance and Site Plan Ordinance.[1]
[1]
Editor's Note: See § 126-133 et seq.
C. 
Any approval may be subject to the condition that the applicant provide and adhere to a detailed construction schedule, copies of which shall be supplied to the Township Engineer and the Township Building Inspector for the purpose of monitoring the progress of the work and compliance with the construction schedule. Said approval may be further conditioned upon submission of periodic certifications by the applicant as to compliance with the construction schedule, and, in the event of noncompliance, written assurance as to the nature and time when steps will be taken to achieve compliance with the construction schedule.
D. 
If the applicant becomes unwilling or unable to comply with the construction schedule or any other requirements or conditions attached to the approval of the application, and the Township Engineer or the Township Building Inspector certifies such unwillingness or inability to the Planning Board, the Planning Board may thereupon revoke approval of the application, after notice and hearing to the applicant, and no further work may be performed on such site with the exception of temporary measures necessary to stabilize the soil and to protect the site from stormwater damage or other hazards created by construction activity on the site.
A. 
To meet the purposes, goals and standards set forth in this Article XXXIV, the applicable provisions of the Zoning Ordinance relating to minimum lot sizes and density of development shall be modified in areas of slopes greater than 10%.
(1) 
The maximum density and FAR modification shall be determined by multiplying the total land area in various slope categories by the following factors:
[Amended 12-5-2005 by Ord. No. 05-55]
Slopes
(percent)
Factor
30 or greater
0.
20-29
0.2
11-19
0.5
0-10
1.0
The resultant acreage is to be used to compute FAR and density.
(2) 
The maximum number of dwelling units allowed on any tract shall be computed as follows:
(Land with slopes of 30% or more x 0)
+ (Land with slopes of 20% to 29% x 0.2)
+ (Land with slopes of 11% to 19% x 0.5)
+ (Land with slopes of 0% to 10%)
= Total Land available for Development (TLD)
TLD
Minimum lot area required/d.u.
=
Total number of dwelling units on tract
B. 
No development or improvements shall be permitted on slopes of 30% or higher. Applicants shall be encouraged to concentrate development on lesser slopes, and the Planning Board, in appropriate cases and with adequate safeguards, may authorize development on lots smaller than permitted in the zone in accordance with the provisions of the Zoning Ordinance regulating cluster development,[1] provided the total number of dwelling units does not exceed the maximum allowed after application of the density modification formula.
[1]
Editor's Note: See Part 12, Article XLVI, § 126-349.
C. 
All land required to be maintained as permanent open space shall be indicated as such on any approved plans.
D. 
All FAR and density shall be based on the area of the property after applying the density computations. Development shall be permitted on the lesser slope area and not on areas of greater slopes.
[Added 12-5-2005 by Ord. No. 05-55]
The maximum impervious surface permitted on steep slopes shall be based on the percentage of slope as follows:
Slopes
(percent)
Maximum Impervious Surface
0-10
As permitted in the Zoning Ordinance[1]
11-19
50% of that permitted in zone
20-29
20% of that permitted in zone
30
No development permitted
[1]
Editor's Note: See Part 12, Zoning.