Compliance. All erosion and sediment control measures indicated on
the certified E&S plan shall be installed and maintained as scheduled.
A cash bond or surety bond to guarantee completion of the control
measures may be required, in an amount to be determined by the Commission
in consultation with the ZEO and/or Wetlands Agent, as appropriate.
If, in the opinion of the ZEO, the control measures have not been
installed or maintained in conformance with the certified plan, the
property owner will be so notified by certified US mail. If the problem,
as described in that notification, is not addressed within 24 hours
of delivery, the ZEO may take steps to correct the problem using funds
from any posted bond.