If the application and plan conform to the requirements of this chapter,
provide for the work to be performed in accordance with the current New Jersey
State Highway specifications and are approved by the Township Engineer, the
Township Clerk shall issue the permit upon receipt of a deposit covering engineering
review and township administration determined as follows:
A. Township administration fee: $20 per application submittal.
B. Engineering review fee: $50 per application submittal.
C. Township Security Deposit Schedule:
|
Type of Road
|
Deposit for 10 Square Feet or Less
|
Additional Deposit per Square Foot in Excess of 10 Square Feet
|
---|
|
Earth or gravel
|
$100
|
$1
|
|
Blacktop or oil and chip
|
$180
|
$5
|
|
Reinforced concrete
|
$300
|
$15
|
|
Concrete sidewalks
|
$50
|
$1
|
|
Concrete curb
|
$75 per
|
$5 10-foot length ($50 minimum)
|
D. In lieu of a security deposit in accordance with the
above schedule, the applicant may deposit the sum of $1,500 in cash with the
Township Clerk.
[Added 4-26-1983 by Ord.
No. O-4-83]
A. When the applicant is a public utility as defined by
the Statutes of the State of New Jersey, the township may accept, in lieu
of required deposits and fees previously set forth herein, a guaranty bond
to the township in the sum of $10,000 plus an application fee of $20 per work
location and $50 per work location for the engineering review fee. For the
purpose of this section, "work location" is defined as any opening or series
of openings in the same street. Each eight-hundred-foot portion of the street
shall constitute a separate work location.
B. In the case of exceptional or complicated openings, or
where the proposed opening involves construction of a longitudinal pipe main
serving more than one property, or in any case where the area to be opened
exceeds 500 square feet, the Township Engineer may, at his discretion, require
the applicant to deposit in cash a certain sum to be placed in escrow by the
township to cover the cost of inspection by professionals employed by the
township. The amount of the initial deposit shall be established by regulation
in an amount reasonably calculated to equal the cost of the necessary inspections.
Sums not utilized in the inspection process shall be returned to the applicant.
If additional sums are deemed necessary, the applicant shall be notified of
the required additional amount and shall add such sum to the escrow. The applicant
must also execute an agreement to underwrite necessary engineering costs incurred
by the township if the repair to the street is unsatisfactory and repair by
the township is necessary.