Entry to perform duties under this bylaw. To the extent permitted
by law, or if authorized by the owner or other party in control of
the property or pursuant to court rule or order, the Stormwater Authority,
its agents, officers, and employees may enter upon privately owned
property for the purpose of performing their duties under this bylaw
and regulations and may make or cause to be made such examinations,
surveys or sampling as the Stormwater Authority deems reasonably necessary.
The Stormwater Authority or its designee shall make inspections
of the work subject to this Bylaw to determine compliance with the
Bylaw and regulations and orders of the Stormwater Authority.
The Stormwater Authority may require the applicant to post before
the start of land disturbance or construction activity or at a specific
time, a surety bond, irrevocable letter of credit, cash, or other
surety acceptable to the Stormwater Authority. The form of the surety
shall be s required and approved by the Stormwater Authority and be
in an amount deemed sufficient by the Stormwater Authority to ensure
that the work will be completed in accordance with the permit. If
the project is phased, the Stormwater Authority may release part of
the bond as each phase is completed in compliance with the permit.
Land disturbance permit. Upon completion of work, the applicant
shall submit a Final Report, including a topographical as-built plan
stamped by a MA Professional Land Surveyor (PLS) and a MA Registered
Professional Engineer (P.E.) as applicable, certifying that the site
has been developed in substantial compliance with the approved plan
including all permanent erosion control devices, stormwater management
facilities and, and any approved changes and modifications. Any discrepancies
from the approved plan should be noted in the cover letter. The final
report shall also include documentation to verify the stormwater management
system has been properly operated and maintained in accordance with
the approved O&M Plan. Discrepancies shall be noted in the cover
letter. The Stormwater Authority may accept said Final Report with
or without conditions or may reject same or may require additional
information before approving said report.