In the event of the damage or destruction by fire, storm or
Act of God of any building or structure not conforming to the regulations
of this chapter, said building or structure may be rebuilt for its
former nonconforming use on its original foundation, provided that
such construction is started within one year from its damage or destruction
and is completed within two years from the date of damage or destruction.
Prior to construction proceeding past placement of the foundation
footings, a plot plan certified by a registered land surveyor shall
be presented to the Code Official showing acceptable setback from
all lot lines. A sketch plan is required at the time the permit is
first requested. (03/1987)
All building permits shall be valid for one year, provided that
the actual building construction applied for has commenced within
six months of the issuance of the permit. An extension may be granted
upon request and with no additional fee. A building permit shall be
required for all alterations and conversions. Building permits are
not transferable.
Building permit fees will be set by the Selectmen.