[Ord. No. 10-2018, 19, passed 3-5-2019]
If damage occurs to concrete sidewalks adjoining newly constructed
curbs, the permittee shall restore the existing sidewalks for the
first full block behind the newly constructed curbs. If the sidewalks
are not suited for repair, as determined by the Engineer, the damaged
sidewalks shall be fully replaced in accordance with the requirements
set forth herein.
[Ord. No. 10-2018, 19, passed 3-5-2019]
(a) A vegetative landscape strip is required when at least 50% of the
sidewalk length along the curb is being replaced at a property. The
landscape strip shall allow for a reduction in impervious area and
reduce stormwater runoff into the street. The width of the landscape
strip shall be at least three feet, unless otherwise permitted by
the Engineer, and shall allow for a minimum sidewalk width of four
feet for pedestrian traffic. The landscape strip shall be planted
with one or more of the following: grass or approved street trees.
Bark mulch may be used in the landscape strip, but decorative stone
is prohibited.
(b) As an alternative to the landscape strip, at least one shade tree
is required for every 40 linear feet of sidewalk that is replaced.
The trees shall be planted in accordance with the specifications provided
in Articles 159 and 1387 of the City's Codified Ordinances. The
use of tree grates and cages must be preapproved by the Engineer due
to the long-term impacts upon tree health by such devices. When used,
tree grates shall be heavy-duty cast-iron, and cast to a form that
is ADA-compliant.
(c) Brick or stamped concrete buffer strips may be constructed only with
the permission of the Director of Public Works.
[Ord. No. 10-2018, 19, passed 3-5-2019]
The minimum clear width of sidewalk is five feet, not including
space occupied by encroachments such as poles, trees, steps, fire
hydrants, etc. In all cases, where possible, new or replacement sidewalk
shall be placed to conform to the abutting sidewalk. The depth of
sidewalk shall be eight inches, including a four-inch crushed stone
foundation and a four-inch concrete slab.
[Ord. No. 10-2018, 19, passed 3-5-2019]
Sidewalks shall be constructed with a 1/4-inch-per-foot (2%)
cross slope extending upward from the curbline to the building line,
unless the Engineer approves a different cross slope due to extenuating
circumstances. If an alternate cross slope is permitted, the sidewalk
shall not adversely impact adjoining sidewalks or properties. At alley
and street corners, the slope may be such as will best meet existing
conditions as approved by the Engineer.
[Ord. No. 10-2018, 19, passed 3-5-2019]
Sidewalk foundations shall be formed at a depth of eight inches
below and parallel to the finish surface of the sidewalk. The subgrade
shall be fine-graded to the proper elevation and compacted to a firm
and unyielding condition. All unstable material, if encountered, shall
be removed to whatever depth required. A four-inch base of thoroughly
compacted PennDOT No. 2B stone (AASHTO No. 5) shall be placed on the
compacted subgrade. All areas within 12 inches of any structure shall
be hand-tamped.
[Ord. No. 10-2018, 19, passed 3-5-2019]
(a) Where existing structures such as light standards, poles, fire hydrants,
water valves, etc., are within the limits of the sidewalk area, the
concrete around such structures shall be formed in a block eight inches
wider than the maximum dimensions of the structure at the sidewalk
elevation. Prior to placing the concrete around such structures, a
1/2-inch premolded expansion joint shall be placed around the structure
for the full depth of the concrete in the walk. Sidewalk openings
for trees are permitted, provided a minimum four-foot clear width
of sidewalk. Sidewalk openings shall be filled to the level of the
adjacent sidewalk with grass, sod or bark mulch on top of a dirt subbase.
(b) It shall be the responsibility of the permittee to reset or have
reset all castings within the limit of his work. All sewer vent caps,
water boxes, gas shutoff boxes, etc., shall be brought to finished
grade. All water boxes, gas shut-off boxes, sewer vent caps, etc.,
if broken during construction, shall be replaced by and/or at the
expense of the permittee.
[Ord. No. 10-2018, 19, passed 3-5-2019]
(a) The concrete driveway apron at depressed curbs shall start at the
back of the curb and transition in grade to the driveway area. The
change in grade between the road surface and sidewalk through the
driveway area shall not exceed 8.00% where there is a non-walk surface
(i.e., landscape strip) between the curb and sidewalk.
(b) A minimum four-foot-wide concrete sidewalk shall be required through
the driveway area, and the sidewalk's cross slope shall not exceed
1/4 inch per foot (2%).
(c) Concrete sidewalk through driveway area shall be 4,000 psi, six inches
in depth and reinforced with 6x6 W2.9xW2.9 welded wire fabric or approved
equivalent. The maximum allowed spacing between joints shall be 10
feet.
(d) All traffic shall stay off driveways for a minimum of seven days.
(e) The design and location of all driveways shall be approved by the
Engineer and Traffic Safety Committee.
[Ord. No. 10-2018, 19, passed 3-5-2019]
Forms shall be wood or metal, straight, free from warp and of
sufficient strength to resist the pressure of the concrete without
springing. If wood, forms shall be two-inch planks surfaced on the
inside and the top. Forms shall have a depth equal to the depth of
the concrete and shall be cleaned and oiled before concrete is placed
against them. Forms that are warped, bent or damaged shall not be
used. The forms shall be perfectly smooth on the side next to the
concrete. The forms shall be accurately placed to the correct line
and grade and rigidly braced. Prior to each use, the forms shall be
thoroughly cleaned to remove cement, dirt and other material.
[Ord. No. 10-2018, 19, passed 3-5-2019]
Concrete sidewalk shall be reinforced with 6x6 W1.4xW1.4 welded
wire fabric or approved equivalent. Concrete sidewalk through driveway
area shall reinforced with 6x6 W2.9xW2.9 welded wire fabric or approved
equivalent. Welded wire fabric shall be set two inches above the stone
base.
[Ord. No. 10-2018, 19, passed 3-5-2019]
(a) Sidewalks shall be constructed in separate slabs 10 to 20 feet in
length for closures. These slabs shall be separated by 1/2-inch transverse
premolded expansion joints for the full depth of the concrete. Expansion
joints 1/2-inch in width shall also be placed longitudinally where
the sidewalk slab is constructed in contact with curbs, building foundations,
concrete porches, concrete steps, etc.
(b) Expansion joints shall be sealed. Clean joints of all scale, dirt,
curing compound, and other foreign material with a mechanized wire
brush. Do not place poured joint-sealing material if the air temperature
is less than 40° F., unless allowed by Engineer. Use heating equipment
of an indirect heating type, constructed as a double boiler. Provide
positive temperature control and mechanical agitation. Obtain the
safe heating temperature and recommended pouring temperature from
the manufacturer's shipping container. Place the material within
this temperature range, but as close as possible to the recommended
pouring temperature. Maintain a single material batch at the pouring
temperature for no more than four hours. Heat the material only once.
Fill the joint reservoir, created by the cleaning operation, with
sealing material to a depth 1/8 inch below the top of sidewalk. Do
not allow sealing material to spread over concrete surfaces.
(c) The slabs between expansion joints shall be divided into blocks five
feet in length, by scoring transversely. Where the slabs are more
than five feet wide, they shall be scored longitudinally in the center.
All scoring shall extend to a depth of one inch. Joint and scoring
edges shall be rounded with a 1/2-inch radius.
[Ord. No. 10-2018, 19, passed 3-5-2019]
(a) After the concrete has been brought to the established grade by means
of a strike-board, it shall be worked with a magnesium wood float
until it is free from depressions and irregularities and provides
a medium rough surface, as directed by the Engineer. Sufficient mortar
shall be brought to the surface for finishing before the concrete
sets. In no case shall dry cement or a mixture of dry cement and sand
be sprinkled on the surface to absorb moisture or to hasten hardening.
(b) Ends of all sidewalks shall be finished square and to a vertical
line and shall not extend beyond property lines or curblines. Side
forms shall not be removed within 24 hours after the concrete has
been placed or until such time as it will not be detrimental to the
concrete, as directed by the Engineer. After stripping the forms,
minor honeycombed areas shall be filled with mortar composed of one
part cement and two parts fine aggregate. Major honeycombed areas
will be considered as defective work and shall be removed and replaced.
(c) After the concrete has sufficiently hardened, the permittee shall
evenly broom-finish the concrete so that the broom strokes are at
90° to the curb. Broom strokes on curb ramps shall be parallel
to the curb.
(d) A swirl finish is also acceptable if the property owner desires such
a finish. A wooden or rubber hand trowel or a magnesium hand float
is acceptable for initial concrete finishing operations.
(e) Impressed cement concrete shall be permitted, if approved by the
Engineer.
[Ord. No. 10-2018, 19, passed 3-5-2019]
After the concrete has sufficiently cured for a period no less
than 72 hours, the spaces adjacent to the sidewalk shall be refilled
with topsoil, mulch and grass in layers of not more than four inches
in depth. Each layer shall be thoroughly compacted to the required
elevation, except for the top 12 inches, which shall remain loosely
compacted for planting. Soils shall be allowed to settle prior to
the planting of vegetation and shall be no higher than the finished
elevation of the sidewalk to assist in stormwater infiltration.
[Ord. No. 10-2018, 19, passed 3-5-2019]
Concrete sidewalks shall be protected and cured in the same
manner as specified for curbs.
[Ord. No. 10-2018, 19, passed 3-5-2019]
In all cases where concrete sidewalks are to be replaced, the
old concrete shall be completely removed over the entire area to be
replaced. The foundation course underneath shall be excavated or filled
up, so as to permit a new slab to be built upon it in accordance with
the specification and of the thickness required for new sidewalk.
[Ord. No. 10-2018, 19, passed 3-5-2019]
(a) Brick paver sidewalks or buffer strips may be constructed only with
the permission of the Director of Public Works. Brick pavers shall
be set with a standard herringbone pattern at 45° with a string
course along each edge. In nonvehicular traffic areas, brick units
shall be set upon a one-inch bed of sand on top of a six-inch compacted
2A crushed stone subbase. Brick joints shall be 1/8 inch (+/-) and
filled with tan-color polymeric sand. The top, bottom and sides of
the crushed stone subbase shall be wrapped with nonwoven geotextile
fabric and turned up against the back side of the curb. In vehicular
areas, the brick units shall be set upon a one-inch bed of sand on
top of a six-inch reinforced concrete slab with a six-inch compacted
2A crushed stone subbase. The concrete slab shall be reinforced with
W2.9x W2.9 welded wire fabric. The bottom and sides of the crushed
stone subbase shall be wrapped with nonwoven geotextile fabric. Geotextile
fabric shall also be placed on top of the concrete slab and turned
up against the back side of the curb.
(b) Where existing brick paver sidewalks or buffer strips are to be replaced,
construction shall be in accordance with the above specifications
for new construction, except that the placement pattern of the brick
pavers shall match the existing pattern of the sidewalk or buffer
strip to be replaced.
(c) Stamped concrete sidewalks and buffer strips may be constructed only
with the permission of the Director of Public Works. The concrete
stamp pattern, surface texture and color shall be approved by the
Director prior to construction.