[Ord. 6 S+FB, 1-13-1995 § 21:3B-1]
No person shall discharge or cause to be discharged any storm
water, surface water, ground water (except as set forth below), roof
runoff, subsurface drainage, uncontaminated cooling water, or unpolluted
industrial process waters to any sanitary sewer.
a. Direct or indirect discharge of ground water to the Joint Meeting
Wastewater Treatment Facilities shall only be permitted under the
following circumstances:
1. The proposed discharger or applicant has filed an application for
and has been issued a Non-Domestic Wastewater Discharge Permit ("Permit")
by the Joint Meeting.
2. For long-term, continuous discharges, the municipality where the
remediation project of the applicant is located or, at the election
of the municipality, the proposed discharger or applicant ("Municipality/Applicant")
will be required to identify and eliminate two gallons of infiltration/inflow
to the Joint Meeting Wastewater Treatment Facilities for each gallon
of ground water to be delivered into the Joint Meeting Wastewater
Treatment Facilities on a daily average over the life of the remediation
project discharge (2 to 1 offset).
(a)
The location(s) of the remedial work to be performed by the
Municipality/Applicant shall be identified by the municipality and
agreed to by the Joint Meeting, through the use of the Phase III Sewer
System Evaluation Report, prepared by Hazen and Sawyer, dated August,
1983 and as supplemented, which was previously distributed by Joint
Meeting to each member municipality in the Joint Meeting service area,
or such other report as may be available in the case of nonmember
municipalities.
(b)
The remedial work to be performed by the Municipality/Applicant
shall be completed within a time period that shall not exceed 1/2
of the time frame of the remediation project discharge estimated by
the proposed discharger or applicant and approved by the municipality
and the Joint Meeting. In the event that extraordinary, unforeseen
circumstances occur that will affect the ability of the Municipality/Applicant
to meet the time period previously agreed upon by the parties for
completion of the infiltration/inflow remedial work, the Municipality/Applicant
may seek an extension of the time period through the filing of a written
request not less than 60 days before a previously defined and agreed
upon milestone, fully describing the extraordinary, unforeseen circumstances
and specifying the additional time necessary to complete the remedial
work as a result thereof. Such requests for extensions will be considered
by the Joint Meeting on a case-by-case basis, and an extension of
time shall not be unreasonably withheld.
(c)
An applicant may not discharge ground water to the Joint Meeting
Wastewater Treatment Facilities until it has obtained a Permit and
an agreement is reached between the Joint Meeting and the municipality
and/or the applicant upon the terms of the remediation work to be
performed to satisfy the 2 to 1 offset policy set forth in this regulation.
(d)
At intervals to be mutually agreed upon by the Municipality/Applicant
and the Joint Meeting, the Municipality/Applicant shall be required
to demonstrate, in written progress reports, to the satisfaction of
the Joint Meeting that the Municipality/Applicant is making definable
progress in performing the remedial work so as to be able to complete
the work within the time frame established in accordance with paragraph
2(b) above.
(e)
The Engineer of the municipality where the remedial work has
been performed will be required to submit to Joint Meeting a certification
stating that remedial work has been completed and such certification
must be submitted within one week of the date of the completion of
the work.
(f)
The Municipality/Applicant will be required to submit to the
Joint Meeting at the time the location(s) of the remedial work is
identified by the municipality and agreed to by the Joint Meeting
a Performance Bond in the amount of 100% of the value of the remedial
work to ensure that such work is completely performed.
3. For short-term batch discharges; delivery:
(a)
For short-term, batch discharges, the Municipality/Applicant
will be required to identify and eliminate two gallons of infiltration/inflow
into the Joint Meeting Wastewater Treatment Facilities for each gallon
of ground water to be delivered to the Joint Meeting Treatment Works
on a daily average over the life of the remediation project discharge
(2 to 1 offset) or
(b)
The material to be discharged from the site of the remediation
project may be delivered in tanker vehicles to the Joint Meeting Wastewater
Treatment Facilities in Elizabeth, New Jersey for direct discharge
at the rate of three cents per gallon, for example, $150 per 5,000
gallon trailer; to compensate Joint Meeting for the costs to sample,
monitor and process the discharge. The use of this option will be
at the reasonable discretion of the Joint Meeting in order to avoid
the arrival of a number of trailers that will adversely impact the
performance of treatment operations by the Joint Meeting.
4. In the event the 2 to 1 offset option is selected with respect to
short-term, batch discharges, then the following procedures shall
apply:
(a)
The location(s) of the remedial work to be performed by the
Municipality/Applicant shall be identified by the municipality and
agreed to by the Joint Meeting, through the use of the Phase III Sewer
System Evaluation Report, prepared by Hazen and Sawyer, dated August,
1983 and as supplemented which was previously distributed by Joint
Meeting to each member municipality in the Joint Meeting service area,
or such other report as may be available in the case of nonmember
municipalities.
(b)
The remedial work to be performed by the Municipality/Applicant
shall be completed within a time period that shall not exceed 1/2
of the time frame of the remediation project discharge estimated by
the proposed discharger or applicant and approved by the municipality
and the Joint Meeting. In the event that extraordinary, unforeseen
circumstances occur that will affect the ability of the Municipality/Applicant
to meet the time period previously agreed upon by the parties for
completion of the infiltration/inflow remedial work, the Municipality/Applicant
may seek an extension of the time period through the filing of a written
request not less than 60 days before a previously defined and agreed
upon milestone, fully describing the extraordinary, unforeseen circumstances
and specifying the additional time necessary to complete the remedial
work as a result thereof. Such requests for extensions will be considered
by the Joint Meeting on a case-by-case basis, and an extension of
time shall not be unreasonably withheld.
(c)
An applicant may not discharge ground water to the Joint Meeting
Wastewater Treatment Facilities until it has obtained a Permit and
an agreement is reached between the Joint Meeting and the municipality
and/or the applicant upon the terms of the remediation work to be
performed to satisfy the 2 to 1 offset policy set forth in this regulation
should this option be selected with respect to a short-term, batch
discharge.
(d)
At intervals to be mutually agreed upon by the Municipality/Applicant
and the Joint Meeting, the Municipality/Applicant shall be required
to demonstrate, in written progress reports, to the satisfaction of
the Joint Meeting that the Municipality/Applicant is making definable
progress in performing the remedial work so as to be able to complete
the work within the time frame established in accordance with paragraph
4(b) above.
(e)
The Engineer of the municipality where the remedial work has
been performed will be required to submit to the Joint Meeting a certification
stating that remedial work has been completed and such certification
must be submitted within one week of the date of the completion of
the work.
(f)
The Municipality/Applicant will be required to submit to the
Joint Meeting at the time the location(s) of the remedial work is
identified by the municipality and agreed to by the Joint Meeting
a Performance Bond in the amount of 100% of the value of the remedial
work to ensure that such work is completely performed.
5. The ground water to be discharged to the Joint Meeting Wastewater
Treatment Facilities pursuant to a Permit will be, at all times, subject
to analyses by the Joint Meeting, at the sole cost of the applicant,
to ensure that the proposed discharge shall meet the quality limits
as set forth in these sewer use rules and regulations. At any time
during the period of the discharge of ground water to the Joint Meeting,
a failure by the applicant to meet such quality limits shall be the
basis for a revocation of the Permit and a discontinuation of the
discharge, and/or such enforcement measures as are authorized by law
to be taken by the Joint Meeting.
6. The proposed discharger or applicant shall be obligated to institute
pretreatment measures prior to the direct or indirect discharge of
ground water to the Joint Meeting in event the ground water fails
to meet the parameters for acceptance of the discharge set forth in
the Sewer Use Rules and Regulations.
7. Credits for future discharges of ground water through the removal
of infiltration/inflow pursuant to the above provisions may be accumulated
or "banked"; however, such credits may only be transferred in accordance
with ownership of the site identified as the source of ground water
at the time of the performance of the remediation work.